Blackbird Energy Pty Ltd v Vanbeelen [2007] QCA 60
JUDGE(S):
Williams JA, Keane JA, Helman J
DELIVERED ON:
02 March 2007
Close
Editorial Notes
Published Case Name:
Blackbird Energy P/L v Vanbeelen
Shortened Case Name:
Blackbird Energy Pty Ltd v Vanbeelen
MNC:
[2007] QCA 60
Court:
QCA
Judge(s):
Williams JA, Keane JA, Helman J
Date:
02 Mar 2007
Litigation History
Event
Citation or File
Date
Notes
Primary Judgment
[2006] QDC 285
23 Jun 2006
Application to recover progress payment by builder pursuant to Building and Construction Industry Payments Act; finding of one contract covering two construction sites allowing the claim to be maintained under s 17(4)(b): Brabazon QC DCJ.
Primary Judgment
[2006] QDC 495
14 Dec 2006
Reasons for orders permanently staying proceeding under Building and Construction Industry Payments Act: Brabazon QC DCJ.
Appeal Determined (QCA)
[2007] QCA 60
02 Mar 2007
Appeal against decision on 23 June 2006 which was permanently stayed on 15 December 2006 (by reasons given on 14 December 2006); can only be reviewed on hypothetical basis; appeal dismissed with costs fixed at $10,000: Williams and Keane JJA and Helman J.
Appeal Status
Appeal Determined (QCA)