Base 1 Projects Pty Ltd v Islamic College of Brisbane Ltd
[2012] QCA 114
To print this judgment please return to the case and click on the PDF icon
next to the
case name. For court use, a full PDF copy is required or preferred.
Please Note: You are about to print a copy of the onscreen
version of
this judgment. For court use, a full PDF copy of the judgment is required or preferred. Please
return to
the case for PDF printing options.
Base 1 Projects Pty Ltd v Islamic College of Brisbane Ltd [2012] QCA 114
JUDGE(S):
McMurdo P, M Wilson AJA, Applegarth J
DELIVERED ON:
24 April 2012
Close
Editorial Notes
Published Case Name:
Base 1 Projects Pty Ltd v Islamic College of Brisbane Ltd
Shortened Case Name:
Base 1 Projects Pty Ltd v Islamic College of Brisbane Ltd
MNC:
[2012] QCA 114
Court:
QCA
Judge(s):
McMurdo P, M Wilson AJA, Applegarth J
Date:
24 Apr 2012
White Star Case:
Yes
Litigation History
Event
Citation or File
Date
Notes
Primary Judgment
SC745/11 (No citation)
05 Sep 2011
The Court ordered that Base 1 Projects Pty Ltd provide security for the costs of its proceedings against the Islamic College of Brisbane Limited in the amount of $90,000 up to and including the first day of trial.
QCA Interlocutory Judgment
[2011] QCA 333
23 Nov 2011
Base 1 appealed the order below. The College applied for an order that Base 1 provide security for costs of the appeal. On the giving of an undertaking by the director of Base 1, the application was dismissed by consent with costs reserved. On the hearing of the reserved costs application, Base 1 was ordered to pay the costs: White JA.
Appeal Determined (QCA)
[2012] QCA 114
24 Apr 2012
Appeal from decision made 5 September 2011 dismissed with costs: McMurdo P, M Wilson AJA, Applegarth J.