CITATION: 

In the making of the Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018 [2019] QIRC 157

PARTIES: 

Rockhampton Regional Council

and

The Australian Workers’ Union of Employees Queensland

CASE NO:

CB/2019/87

PROCEEDING:

Application for certification of an agreement

DELIVERED ON:

25 October 2019

HEARING DATE:

25 October 2019

HEARD AT:

Brisbane

MEMBER:

McLennan IC

ORDER:

  1. The Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018 is certified.

CATCHWORDS:

INDUSTRIAL LAW – COLLECTIVE BARGAINING – Application for certification of an agreement – Requirements for certification – Agreement certified

LEGISLATION:

Industrial Relations Act 2016

APPEARANCES:

Ms S. Mitanis of the Local Government Association Queensland on behalf of the Rockhampton Regional Council

Ms S. Young of The Australian Workers’ Union of Employees Queensland

Reasons for Decision

  1. [1]
    The Rockhampton Regional Council has made an application to certify an agreement pursuant to s 189 of the Industrial Relations Act 2016 ("the Act"). As required by s 189(3) of the Act, the application was made within 21 days of the date on which the agreement was signed.
  1. [2]
    The agreement is made between the Rockhampton Regional Council and The Australian Workers’ Union of Employees Queensland.
  1. [3]
    The Commission is satisfied that all parties have agreed on the terms of the agreement, which were approved by a valid majority of relevant employees in a properly conducted ballot. The application for certification was made within a reasonable time after the proposed agreement was approved.
  1. [4]
    The agreement shall apply to persons employed at Rockhampton Regional Council’s treatment plant.
  1. [5]
    In certifying the agreement, the Commission has regard to the submissions of the parties and the affidavit of Mr. Evan Anthony Pardon, Chief Executive Officer of Rockhampton Regional Council, sworn 2 September 2019.
  1. [6]
    The Commission determines that each relevant requirement under sub-div 2 of div 2 of pt 5 of the Act has been satisfied. Further, there is nothing in the agreement which would require the Commission to refuse to grant the application under sub-div 3 of div 2 of pt 5 of the Act.
  1. [7]
    The agreement operates from the day it is certified, namely 25 October 2019 and, although the nominal expiry date of the agreement is 1 July 2022, it continues to operate until it is terminated under s 227 or s 228 of the Act. 
  1. [8]
    The application to certify the Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018 is granted.
  1. [9]
    I make the following order:
  1. The Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018 is certified.
Close

Editorial Notes

  • Published Case Name:

    In the making of the Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018

  • Shortened Case Name:

    In the making of the Rockhampton Regional Council Treatment Plant Operators Certified Agreement 2018

  • MNC:

    [2019] QIRC 157

  • Court:

    QIRC

  • Judge(s):

    Member McLennan IC

  • Date:

    25 Oct 2019

Appeal Status

Please note, appeal data is presently unavailable for this judgment. This judgment may have been the subject of an appeal.

Require Technical Assistance?

Message sent!

Thanks for reaching out! Someone from our team will get back to you soon.

Message not sent!

Something went wrong. Please try again.