Queensland Judgments
Authorised Reports & Unreported Judgments
Exit Distraction Free Reading Mode
  • Unreported Judgment

Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission[2021] QDC 77

Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission[2021] QDC 77

DISTRICT COURT OF QUEENSLAND

CITATION:

Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission [2021] QDC 77

PARTIES:

FULL BUILDING SOLUTIONS PTY LTD ACN 602 269 330

(first applicant)

and

KYLIE ANNE BURT (WYATT)

(second applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

FILE NO:

221/20

DIVISION:

Appellate

PROCEEDING:

Appeal pursuant to s 45 Magistrates Court Act 1921 (Qld)

ORIGINATING COURT:

Magistrates Court, Brisbane

DELIVERED ON:

22 June 2021

DELIVERED AT:

Cairns

HEARING DATE:

30 April 2021

JUDGE:

Fantin DCJ

ORDERS:

  1. Grant leave to appeal for the sole purpose of correcting the order made by the Magistrates Court on 30 October 2020.
  2. Otherwise dismiss the application for leave to appeal.
  3. The applicants pay the respondent’s costs of the application for leave to appeal and appeal on the standard basis.

CATCHWORDS:

APPEAL – CIVIL – PROCEDURAL – PROFESSIONS & TRADES – BUILDERS – STATUTORY INSURANCE SCHEME – where the first applicant was contracted to do residential building work – where the second applicant was the director of the first applicant – where the homeowner made a complaint of defective work – where the respondent gave a direction to rectify – where the first applicant did not comply with the direction– where the respondent engaged a consultant who invited tenders to carry out the rectification work – where the respondent made a payment under the statutory insurance scheme – where the respondent sought to recover that amount as a debt pursuant to ss 71 and 111C of the Queensland Building and Construction Commission Act 1991 (Qld) – where summary judgment for that debt was entered for an amount less than the “minor civil dispute limit” – where the form of the order was irregular or defective

District Court Act 1967 (Qld) ss 92, 113

Magistrates Court Act 1921 (Qld) s 45

Uniform Civil Procedure Rules 1999 (Qld) rr 166, 190,  292, 302, 388, 460, 659, 660, 765, 766, 783, 785.

Queensland Building and Construction Commission Act 1991 (Qld) ss 71, 74, 111C

Agar v Hyde (2000) 201 CLR 552

American Express International Inc v Hewitt [1993] 2 Qd R 352

Baker v Arkman Pty Ltd [2014] QDC 165

Best Price Real Estate Pty Ltd v Equity 2 Pty Ltd [2021] QCA 99

Bolton Properties Pty Ltd v J K Investments (Australia) Pty Ltd [2009] 2 Qd R 202

Deputy Commission of Taxation v Salcedo [2005] 2 Qd R 232

Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 192

Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87

Jonathan v Mangera [2016] QCA 86

Johns v Johns [1988] 1 Qd R 138

Mahony v Queensland Building Services Authority [2013] QCA 323

Murdoch v Alex Mackay & Co [2017] QDC 81

Namour v Queensland Building Services Authority [2015] 2 Qd R 1

Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd & Anor [2014] QCA 161

Queensland Building Services Authority v Orenshaw & Anor [2012] QSC 241

Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in liq) [2003] 1 Qd R 259

Ramzy v Body Corporate for GC3 CTS38396 & Anor [2012] QDC 397

Wanstall v Burke [1925] St R Qd 295

Willmot & Anor v McLeay & Anor [2013] QCA 84

COUNSEL:

The applicants were self represented.

J Eylander for the Respondent.

SOLICITORS:

The applicants were self represented.

Robinson Locke Litigation Lawyers for the Respondent.

Nature of the proceeding

  1. [1]
    This is an application for leave to appeal against a decision of Acting Magistrate Springer on 30 October 2020 to order summary judgment in favour of the respondent pursuant to r 292 of the Uniform Civil Procedure Rules 1999 (Qld) (UCPR).
  1. [2]
    Pursuant to s 45(2)(a) of the Magistrates Court Act 1921 (Qld) (MCA) leave is required because the amount of the judgment was not more than the “minor civil dispute limit”, which is $25,000.[1] In such a case, the court “shall not grant such leave to appeal unless the court is satisfied that some important principle of law or justice is involved”: s 45(2)(a) MCA.
  1. [3]
    Both the application for leave to appeal and the appeal were heard together.
  1. [4]
    Leave should be granted for the sole purpose of correcting an error in the form of the order. Otherwise, the application for leave should be refused because no important principle of law or justice arises and, in any event, no error by the Acting Magistrate has been shown.

Background

  1. [5]
    The proceeding arises out of a dispute about residential building work carried out by the first applicant, a building company, for a homeowner in 2017.
  1. [6]
    The respondent sought to recover from the applicants payments made under the home warranty scheme, a compulsory statutory compensation scheme for residential construction work carried out in Queensland.
  1. [7]
    The second applicant, Ms Wyatt, was the sole director of the first applicant. Under the relevant legislation, every licensed company must have a nominee, being the person holding the technical qualifications for the company and must hold a licence in their own right. That person was Mr Wyatt. He is not a party to the proceeding.
  1. [8]
    The homeowner complained that the residential building work was defective. The complaint was referred to the statutory insurance scheme under the Queensland Building and Construction Commission Act 1991 (QBCC Act).
  1. [9]
    The respondent determined that the work was defective, and issued a direction to rectify. The first applicant sought an internal review of that decision. The review decision found that the first applicant was liable to rectify the defective work. The respondent issued a fresh direction to rectify. The first applicant did not comply with it. The dispute was referred to the insurance division under the home warranty insurance scheme. The respondent issued a scope of work for rectification of the defective work and engaged a consultant to manage the rectification work and source quotes. The respondent accepted a quote for rectification of the defective work and ultimately paid $16,017.60 under the home warranty insurance scheme for the rectification work. The respondent sought to recover that amount from the applicants.
  1. [10]
    On 21 May 2020 the respondent filed a claim and statement of claim against the applicants claiming $16,017.60 plus interest and costs.
  1. [11]
    On 16 June 2020 the applicants filed a Notice of Intention to Defend and document entitled “Statement of Claim” but which was, in truth, their Defence. The document was not drafted with the benefit of legal advice, did not use legal terms, and did not comply with the rules of pleading in the UCPR. Nonetheless, it pleaded material facts sufficiently to understand the applicants’ position.  The document also attached a number of documents.
  1. [12]
    In that document, the applicants admitted a number of allegations of fact but sought to review the steps taken by the respondent under Parts 5 and 6 of the QBCC Act.   They also asserted that the first applicant did not fail to rectify defective work, that the respondent failed to disclose relevant documents, that the tender price accepted by the respondent was unreasonable and inflated, that the first applicant’s nominee, Mr Wyatt, suffered an injury that resulted in him being unable to work, and that the applicants were unable to respond to the complaint at the relevant time and were suffering financial hardship.
  1. [13]
    On 17 July 2020 the respondent filed a Reply.
  1. [14]
    On 17 September 2020, the respondent filed and served an application for summary judgment and supporting affidavit. Summary judgment was sought pursuant to r 190(1) and (2) UCPR on the basis of pleaded admissions and deemed admissions pursuant to r 166(1) UCPR.
  1. [15]
    On 13 October 2020 the applicants filed an affidavit of Mr Wyatt.
  1. [16]
    On 30 October 2020 the application for summary judgment was heard. The applicants did not appear. Summary judgment was entered against them pursuant to rule 292 UCPR. The applicants were ordered to pay the amount claimed plus interest and costs on an indemnity basis.
  1. [17]
    Where judgment is given on an application for summary judgment against a party who did not appear on the hearing of the application, that party may apply to the court pursuant to r 302 UCPR to set aside the summary judgment.  In such an application it is relevant, but not an essential pre-condition, for the applicant to explain the reason for failing to attend the hearing where the court gave the judgment. Here the applicants did not apply to set aside the summary judgment under r 302. That is unsurprising given that there was affidavit evidence from Mr Wyatt indicating they did not intend to appear on the hearing.
  1. [18]
    The claim and statement of claim upon which summary judgment was based sought an amount less than $25,000, and summary judgment was ultimately given for an amount less than $25,000. The respondent’s claim was for recovery of a liquidated sum of $16,017.60 (payments made by the respondent on a claim under the statutory insurance scheme) plus interest of $1,618.10, resulting in a total amount claimed of $17,635.70.[2]

Form of Order

  1. [19]
    The order for summary judgment was made by being pronounced in court by the Magistrate. The order took effect as of the date on which it is made: r 660 UCPR.  The Acting Magistrate amended a draft order provided by the respondent’s solicitor. The respondent’s draft order did not specify the amount of the judgment nor the amount of interest.
  1. [20]
    The order signed by the registrar and filed in the court embodying the order made by the Magistrate on 30 October 2020 was headed “Order” in form 59, and simply stated “Summary judgment be granted in favour of the Plaintiff against the Defendants pursuant to Rule 292 of the Uniform Civil Procedure Rules 1999.”
  1. [21]
    The form of order is defective or irregular because it did not specify the amount for which summary judgment was entered nor the amount of interest: see Form 58 of the Approved Forms, r 659 UCPR, and Best Price Real Estate Pty Ltd v Equity 2 Pty Ltd [2021] QCA 99 at [15].
  1. [22]
    It is arguable that the irregularity could be cured by the slip rule in r 388. Rule 460 allows a registrar to apply the slip rule to an order if there is a clerical mistake or an error in the record which occurred as a result of an accidental slip or omission, on their own initiative, or by way of application by a party. The power to correct a clerical mistake or error may be exercised at any time, even after a judgment or order has been made.
  1. [23]
    I was unassisted by submissions or authority on this issue. In those circumstances, the appropriate course is to grant leave to appeal for the sole purpose of correcting the form of the order.
  1. [24]
    The order of the Magistrates Court of 30 October 2020 should be corrected in accordance with UCPR form 58, Judgment, to state:

“The judgment of the court is that:

  1. The Defendants pay to the Plaintiff the amount of $17,635.70 comprising the sum claimed of $16,017.60 and interest of $1,618.10 to this day.
  2. The Defendants pay the Plaintiff’s costs of the proceeding, including the application for summary judgment, to be assessed on an indemnity basis.
  1. [25]
    For the reasons articulated below, I would otherwise refuse leave to appeal.

Relevant legal principles

  1. [26]
    The test for leave to appeal under s 45(2)(a) MCA was considered by Bowskill QC DCJ (as Her Honour then was) in Murdoch v Alex Mackay & Co [2017] QDC 81 at [13]-[14]:

[13] As explained by McGill SC DCJ in Ramzy v Body Corporate for GC3 CTS 38396 [2012] QDC 397 at [41]-[42],[3] the test laid down by this provision is one of not granting leave to appeal unless the court is of the opinion that the case is one of gravity, or involving some important question of law, or affecting property of considerable value; or unless it is a case which is otherwise of public importance, or is of a very substantial character”.[4]

[14] Further, in American Express International Inc v Hewitt [1993] 2 Qd R 352 at 353, Davies JA observed that:

“…when s 92(2) [the equivalent provision in the District Court Act 1967 then in force] speaks of an important question of justice, it is not speaking merely of the injustice which a party will generally suffer when a decision is made against that party which appears to be wrong. It is speaking of a question which goes beyond the correctness or otherwise of the decision… Merely demonstrating that a decision is arguably or even probably wrong does not establish that an important question of justice is involved.”

  1. [27]
    I agree that this is the test to be applied.
  1. [28]
    The applicants were self represented in the court below and this court. They filed outlines of argument and various documents in support of their application for leave to appeal and appeal. The second applicant, Ms Wyatt, appeared and made oral submissions on the hearing in this court.
  1. [29]
    Chapter 18, r 783 UCPR outlines the procedure for appeals to the District Court from the Magistrates Court.
  1. [30]
    On such an appeal, this court has the same powers as the Court of Appeal to hear an appeal: s 113 District Court Act 1967 (Qld) (DCA); rules 785, 765(1) UCPR.
  1. [31]
    The decision of a court to grant summary judgment pursuant to r 292 UCPR is an exercise of discretion which depends upon the determination, in the first instance, of the mandatory pre-conditions for any such exercise of discretion. Pursuant to rule 292(2) UCPR, they are that the defendant has no real prospect of successfully defending all or a part of the plaintiff’s claim and that there is no need for a trial of the claim or part of the claim. 
  1. [32]
    Ordinarily it is necessary, if the court is to intervene to exercise any power available to it, that error be identified in the decision of the Acting Magistrate, such as to warrant intervention[5].   An appellate Court will only interfere with the exercise of a discretion if it is shown that the primary Judge acted on a wrong principle, failed to take a material consideration into account or took into account an immaterial consideration.
  1. [33]
    The principles guiding the exercise of the court’s discretion to order summary judgment are well settled. The power should be exercised with great care, and should never be exercised unless it is clear that there is no real question to be tried[6].  Summary judgment will not be granted as a matter of course[7]. It should not be granted “except in the clearest of cases”[8]. That is because ordinarily a party is not to be denied the opportunity to place his or her case before the court in the ordinary way, and after taking advantage of the usual interlocutory processes[9].  The question is whether there exists a real, as opposed to a fanciful, prospect of successfully defending the claim[10].
  1. [34]
    The test requires a high degree of certainty about the ultimate outcome of the proceeding if it were allowed to go to trial in the ordinary way[11].  The discretion does not arise merely because the court concludes that a successful defence is improbable[12].
  1. [35]
    In this case, the applicants face the additional hurdle that it is not enough for them to demonstrate merely that the decision below is arguably or even probably wrong. In order for leave to be granted, they must satisfy the court that an “important question of law or justice is involved”.

Grounds of appeal and application for leave to appeal

  1. [36]
    Doing the best I can to summarise the grounds of appeal and submissions, the applicants:
  1. Contend that they were denied natural justice and not given an opportunity to be heard in the Magistrates Court;
  2. Challenge the respondent’s previous process and decisions on a number of bases:
  1. (a)
    the respondent failed to properly consult the applicants;
  1. (b)
    the respondent failed to consider whether the alleged defective work was carried out by the first applicant or previous builders,
  1. (c)
    the terms of the direction to rectify;
  1. (d)
    the process for rectification of defective work;
  1. (e)
    the scope of works, what work was being tendered for, and the price of the tenders; and
  1. (f)
    the qualifications or expertise of the inspector.
  1. Seek a hearing de novo of the proceedings the subject of the application for leave to appeal.

Application to adduce further evidence

  1. [37]
    The applicants’ outline of submissions on appeal attached various documents. They included an affidavit from an employee carpenter, an affidavit from a cabinet installer containing hearsay, character references from two builders, documents printed from the internet, a data stick said to contain evidence of a meeting in October 2017, and a QBCC licence search of the inspector (“the documents”).
  1. [38]
    The court may on special grounds receive further evidence as to questions of fact: r 766(1)(c) UCPR. The party seeking to adduce such evidence must satisfy the court that the evidence[13]:
  1. could not have been obtained by reasonable diligence for the original hearing;
  2. if allowed, would have an important impact or influence on the case; and
  3. is apparently credible.
  1. [39]
    Some of the documents were inadmissible because they were irrelevant or contained hearsay. To the extent the documents may have included admissible material, that material was in the possession of the applicants and pre-dated the hearing in the Magistrates Court. There was no reason why the documents could not have been obtained by reasonable diligence for that hearing in the Magistrates Court on 30 October 2020 and adduced at that time in admissible form. Without sworn evidence explaining some of the documents, I could not be satisfied that they were apparently credible.
  1. [40]
    Importantly, I am not satisfied that, if allowed in the form in which they were sought to be adduced, the documents would have an important impact or influence on the case. That is because of the legal hurdles faced by the application for leave to appeal discussed below.
  1. [41]
    The applicants have failed to satisfy the relevant test. Their application to adduce further evidence on appeal is refused.

Consideration

Denial of natural justice in Magistrates Court? 

  1. [42]
    The applicants contended that that they were denied natural justice and not given an opportunity to be heard in the Magistrates Court. They submitted that they were not contacted by the Magistrates Court, not notified of the hearing date, and not given the opportunity to be heard on the hearing.
  1. [43]
    Those submissions cannot be accepted because they are contrary to the evidence.
  1. [44]
    The summary judgment application and respondent’s outline of submissions were served on the applicants by email to their nominated email address. The applicants clearly had notice of the hearing date of 30 October 2020.
  1. [45]
    On 13 October 2020 the respondent’s solicitors wrote to the applicants advising them that it had established an entitlement to summary judgment and they had no real prospect of defending the claim. It enclosed a formal offer to settle under the UCPR.
  1. [46]
    In response to the application for summary judgment, the applicants filed an affidavit of Mr Wyatt of 13 October 2020. He deposed that the applicants were unable to attend the hearing in person due to financial hardship and his medical condition. He deposed that the building consultant was not qualified to inspect, accept, review or recommend rectification of the building works. He challenged the quotation for rectification of the works accepted by the respondent on the basis that it was overpriced.
  1. [47]
    On 29 October 2020, the respondent’s solicitor emailed the applicants advising of its objections to the affidavit of Mr Wyatt, noting that the respondent would be proceeding with the hearing of the application on 30 October 2020, and advising the applicants they could apply to appear by telephone at the hearing.
  1. [48]
    On 30 October 2020 at the hearing of the application, the applicants did not appear. The respondent’s solicitor drew to the Acting Magistrate’s attention Mr Wyatt’s affidavit and the information that the applicants did not intend to appear. The transcript shows that the Acting Magistrate stood the matter down to later in the day so that attempts could be made to contact the applicants. When the matter resumed, two attempts were made to call the mobile telephone number provided by Ms Wyatt. Both calls went to voicemail.
  1. [49]
    The respondent provided to the Acting Magistrate an affidavit of service, a written outline of argument, a list of cases and relevant statutory provisions, and a table of objections to Mr Wyatt’s affidavit. The transcript records that the Acting Magistrate read all of the relevant material before making her decision. She heard oral submissions from the respondent’s solicitor. The Acting Magistrate read the affidavit of Mr Wyatt and took it into account, notwithstanding the objections to it.
  1. [50]
    The Acting Magistrate delivered ex tempore reasons. She was satisfied on the basis of the material that the applicants had no real prospect of defending the claim and that there was no need for a trial.  She made orders in accordance with the draft provided. Upon proof of the respondent’s formal offer to settle, the Acting Magistrate ordered costs on an indemnity basis.
  1. [51]
    The applicants could have sought leave to appear by audio or audio-visual link at the hearing but chose not to do so. The Acting Magistrate was entitled to proceed in their absence. The applicants were not denied natural justice in the Magistrates Court.

No real prospect of defending the claim?

  1. [52]
    The applicants sought to challenge the previous process of, and decisions made by, the respondent on the basis that there were unfair and lacked transparency including by:
  1. Failing to properly consult them and not agreeing to change the date for a site inspection when requested;
  2. Considering whether the alleged defective work was carried out by the first applicant or previous builders;
  3. the terms of the direction to rectify;
  4. the process for rectification of defective work;
  5. the scope of works, what work was being tendered for, and the price of the tenders; and
  6. the qualifications or expertise of the inspector.
  1. [53]
    The pleadings and affidavit evidence in support of the summary judgment application established the following matters.
  1. [54]
    The second applicant was a director of the first applicant, which held licence number 1286586 in the classes Builder - Low Rise, Carpentry, Joinery, and Shopfitting.
  1. [55]
    On or about 25 June 2017 the first applicant entered into a cost plus contract for residential construction work with the homeowner. The estimated cost of the works was $55,000 plus GST based upon an agreed hourly rate.
  1. [56]
    On 26 June 2017 the first applicant notified the respondent that the building works were to be undertaken for the homeowner and paid the insurance premium for cover for the building work under the Queensland Home Warranty Scheme.[14] The respondent issued a Notice of Cover to the first applicant and the homeowner, confirming a policy of insurance for the building works was in existence under the scheme.
  1. [57]
    The first applicant carried out the building works, which were completed in late July 2017.
  1. [58]
    On 18 August 2017 the homeowner’s agent, a building designer, notified the first applicant of concerns about defective building work.
  1. [59]
    On 2 September 2017 Mr Wyatt on behalf of the first applicant responded to those concerns.
  1. [60]
    On or about 11 September 2017 the respondent received a complaint from the homeowner alleging defective and incomplete building work.
  1. [61]
    On 26 September 2017 the respondent notified the first applicant of a site inspection at 8:30am on Monday 9 October 2017. The night before the site inspection, the applicants advised the respondent that they could not attend the site inspection and apologised for the late notice.
  1. [62]
    The site inspection went ahead on 9 October 2017. The respondent’s building inspector identified defective building work performed by the first applicant. The applicants did not attend the site inspection but met with the respondent soon after to discuss the site inspection and alleged defects. The applicants obtained a quotation from another contractor dated October 2017 to rectify the alleged defective work, which was for $2,820.24. The first applicant could have, but did not, engage that contractor to carry out the rectification work.
  1. [63]
    On 2 November 2017 the respondent issued a Direction to Rectify and/or Complete No. 0102759 (“the first direction”). It directed the first applicant to rectify certain defective or incomplete building work by 6 December 2017. It advised the first applicant that should it fail to comply with the direction, any outstanding works may be completed under the Queensland Home Warranty Scheme and the respondent may seek recovery for any payment made for an approved insurance claim including by legal action against the first applicant and any of its directors. The direction advised the first applicant that it had a right to seek external review of the decision by the Queensland Civil and Administrative Tribunal (QCAT) and a right to seek internal review by the respondent.
  1. [64]
    The first applicant sought an internal review of the direction. The respondent conducted an internal review of the direction.
  1. [65]
    On 11 December 2017 the internal review upheld the direction with a new Direction to Rectify and/or Complete No. 0102908 (“the second direction”) issued on 15 December 2017. It required the first applicant to rectify the defective work by 2 February 2018. By the second direction, the respondent advised the first applicant it had a right to seek external review in QCAT.
  1. [66]
    The first applicant did not seek an external review in QCAT and did not comply with the second direction.
  1. [67]
    On 7 February 2018 the respondent notified the first applicant that the case would be assessed as a claim under the home warranty scheme and that the respondent may seek recovery from the first applicant. The respondent appointed a building consultant to assess what work was needed, arrange quotes and manage the works.
  1. [68]
    On 6 March 2018 the respondent sent the Scope of Works to the first applicant advising that it would be used to obtain quotations to determine the amount of the claim. The respondent invited the first applicant to contact it to discuss any concerns. The document also advised the first applicant that it could seek external review in QCAT or internal review by the respondent.
  1. [69]
    The first applicant did not seek external review or internal review and did not respond.
  1. [70]
    On 4 June 2018 the respondent received a tender assessment report from the building consultant which attached tenders for rectification works. Tenders were received from two contractors. The consultant recommended that the lower of the two tenders be accepted. That occurred.
  1. [71]
    On 12 July 2018 the respondent advised the first applicant that the amount of $14,455.65 had now been approved for rectification of the works. Again the respondent advised the first applicant that under s 71 of the QBCC Act, the respondent was entitled to recover the amount paid on the claim from the first respondent.
  1. [72]
    On 29 October 2018, the respondent made payments totalling $16,017.60 under the Home Warranty Insurance Scheme in connection with the homeowner’s claim (comprising the tender price of $14,455.65 and the consultant’s fees of $1,561.95).
  1. [73]
    On 4 February 2019 the respondent made a demand to the applicants for payment of $16,017.60. The applicants did not pay any of the amount claimed.
  1. [74]
    The following facts were admitted or not disputed by the applicants:
  1. The first applicant was the relevant “building contractor” for the purposes of s 71(1) of the QBCC Act;
  2. the second applicant was the director of the first applicant;
  3. there was a contract between the first applicant and the homeowner for residential construction works, signed by the first applicant’s nominee, Mr Wyatt, on behalf of the first applicant;
  4. a policy of insurance came into effect in relation to the building works which indemnified the homeowner against defective work performed by the first applicant;
  5. the first applicant performed the works the subject of the contract;
  6. the first applicant was paid in full under the contract;
  7. the respondent received a complaint from the homeowner of defective work;
  8. the first applicant did not comply with the relevant directions to rectify;
  9. the first applicant did not seek an external review in QCAT of the direction to rectify, the decision of failure to rectify, or the scope of works;
  10. the respondent paid the relevant sum under the statutory insurance scheme, and now claims that sum from the applicants; and
  11. the applicants have not paid that sum.
  1. [75]
    Section 71 of the QBCC Act provides that if the commission makes any payment on a claim under the statutory insurance scheme, the commission may recover the amount of the payment, as a debt, from the building contractor by whom the relevant residential construction work was, or was to be, carried out or any other person through whose fault the claim arose.
  1. [76]
    Subsections 71(4), (5) and (6) of the QBCC Act identify potential defences to such a claim. For example, it is a defence for the licensed contractor to prove that the licence card was imprinted on the contract, or its name and licence number were used, without authority.  None of those sections were pleaded in the defence, nor are they said to be relevant or applicable.
  1. [77]
    Subsections 111C(3) and (6) are the basis for the director’s liability. They provide that that if a company owes the commission an amount because of a payment made by the commission on a claim under the insurance scheme, the liability to pay the amount attaches to each individual who was a director of the company when building work the subject of the claim was, or was to have been, carried out, and who was a director when the payment was made by the commission. Therefore, a director of a company which is a building contractor will be liable in defined circumstances to make a payment which otherwise would be payable only by the company. In this case, there was no dispute that the second applicant was the sole director at the relevant times.
  1. [78]
    The issues raised by the applicants in their defence in the Magistrates Court in effect sought a merits review of the process conducted, and decisions made, by the respondent.
  1. [79]
    There is clear authority that a merits review of decisions with respect to a direction to rectify, failure to rectify, and Scope of Works is not justiciable (that is, capable of being decided by the court) in s 71(1) recovery proceedings.
  1. [80]
    In Mahony v Queensland Building Services Authority[15] a contractor sought to defend a claim under s 71(1) by challenging the anterior steps taken by the respondent in the assessment of the claim, including the competency and qualifications of the inspector who prepared the report. The Court considered whether in those proceedings a contractor could challenge such matters, including an inspection report, a decision to direct rectification of work, a decision that rectification work had not been satisfactorily attended to, and a decision to accept a particular tender from those submitted for rectification work.[16]  Gotterson JA held (McMurdo P and Douglas J agreeing) that those matters were not justiciable in s 71(1) recovery proceedings:

“[34] Section 71(1) confers a right to recover as a debt from any of the designated persons “any payment on a claim under the insurance scheme”. It is sufficient for recovery under the section that the authority have made a payment on a claim under the insurance scheme. The statutory right to recover is not conditioned upon the legal quality of a determination by the authority to make the indemnity payment or of any anterior step taken by the authority that had led to the decision to pay.

[35] That is not to say that a decision to make an indemnity payment or any anterior step is not reviewable. At the relevant time, Division 3 of Part 7 of the QBSA Act conferred a review jurisdiction on the Commercial and Consumer Tribunal (“the Tribunal”) with respect to the following decisions by the authority: to direct or not direct rectification or completion work on a building; that work undertaken at the direction of the authority was not of a satisfactory standard; about the scope of works to be undertaken under the statutory insurance scheme in order to rectify; and to disallow a claim under the scheme wholly or in part. A decision by the authority to recover an amount under s71(1) was not reviewable by the Tribunal. However, it was a decision which was judicially reviewable in the Supreme Court of Queensland pursuant to the provisions of the Judicial Review Act 1991. So, too, for other anterior decisions of the authority. The availability of review of those kinds and at those stages provides a sound rationale for a legislative intention that the types of decisions to which I have referred, not be justiciable in s71(1) debt recovery proceedings. Another indicator of such an intention is that s 71 itself specifies certain defences which may be raised in proceedings under the section. None of these are relevant to the kind of defence that the appellant would wish to agitate in these proceedings.” [footnotes omitted]

  1. [81]
    Henry J observed in Queensland Building Services Authority v Orenshaw & Anor[17] that:

“At the other extreme, it is unlikely that s 71 could be avoided by a building contractor disputing discretionary factual conclusions occurring as part of the professional judgment exercised by the QBSA in deciding whether and how much to pay in respect of a claim. It would not be enough to avoid the statutory liability imposed by s 71 for a defendant to point merely to an error of fact connected with the claim process. It must logically have been a factual error of such a nature that the claim was not, on the facts correctly known, a claim under the insurance scheme or that the payment sought to be recovered was not a payment on such a claim.”

  1. [82]
    The applicants could have, but did not, seek to review or challenge those anterior decisions before the respondent paid out under the insurance policy.
  1. [83]
    For the reasons given in the authorities above, the applicants may not now in these proceedings or in their defence in the Magistrates Court challenge those decisions on the grounds proposed.
  1. [84]
    The Court of Appeal in Namour v Queensland Building Services Authority[18] affirmed this aspect of the court’s reasoning in Mahony. Fraser JA (with whom McMurdo P and Douglas J agreed) stated:

[19] The scheme of the Act is that a building contractor or other interested person who wishes to challenge such decisions should make the challenge before the respondent pays under the policy. A building contractor who does not make such a challenge is liable under s71(1) whether or not one of those anterior decisions might have been the subject of a challenge. In the case of a building contractor which is a company, a director caught by s111C(6) is similarly unable to challenge one of those anterior decisions in a proceeding for recovery of a debt. This is so because the director’s liability is fixed by reference only to the liability of the building contractor.”

  1. [85]
    In Namour, the contractor argued that the provisions for review might be availed of in “an ideal world” but that he lacked the financial resources and information necessary to seek review of the relevant decision. Fraser JA said:

“[20] The appellant’s own evidence was instead that he did not “pursue a review of the decision to cancel the Company’s licence at the time of cancellation because Sean Fitzpatrick was looking after the financial affairs of the company, as he was the Managing Director of the Company. Unbeknownst to me, Sean Fitzpatrick resigned as Director in December 2007.” … More fundamentally, this argument did not come to grips with the scheme of the Act that challenges to such decisions should be made well before a recovery proceeding is brought against the contractor or directors.”

  1. [86]
    A similar submission was made in this case. There was evidence that in April or June 2018 the first applicant’s nominee, Mr Wyatt, suffered a serious injury at work and was left with a disability.[19] He required medical treatment and was unable to work. Mr Wyatt and the second applicant, Ms Wyatt, were dealing with personal and financial stressors which made it difficult for them to give their attention to the rectification of defective work and the respondent’s process.  While that is unfortunate, it does not provide the applicants with a legal basis upon which to defend the respondent’s claim nor to seek leave to appeal the Acting Magistrate’s decision.   Nor does it explain why the applicants did not deal with the issues raised by the respondent, or seek external review of the respondent’s decisions, between September 2017 and when the injury occurred in April or June 2018.
  1. [87]
    In Namour the court also held that neither the reasonableness of a payment made by the respondent nor the amount owing by a claimant under the insurance scheme to the contractor is made a criterion of liability under s 71(1).[20] Those criteria would be relevant in a recovery action under s 71(1) only if they were relevant to the determination of the question whether the amount sought to be recovered by the respondent is the amount of the “payment on a claim under the insurance scheme”. 
  1. [88]
    The Court in Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd & Anor[21] (Gotterson JA, McMurdo P and Ann Lyons J agreeing) said that:

“The decision in Mahony supports the view that the right to recover conferred by s 71(1) is not conditioned upon the legal quality of any step that the respondent may have taken antecedent to a decision to make payments under the scheme.”

  1. [89]
    The court also considered the circumstances in which anterior steps may be relevant in a recovery proceeding:

“[34] Whilst the right to recover under s 71(1) is not conditioned as Lifetime Securities submits that it is, that is not to say that compliance by QBCC with the provisions of Part 6 might never have potential relevance to a recovery action under s71(1). For example, such a circumstance might arise in the following way. Under the Insurance Policy Conditions, the amount that QBCC may pay under the insuring clause is limited to the reasonable cost, as determined by QBCC, of undertaking the rectification work: clause 4.2(a). A failure on the part of QBCC to call tenders when it was required to do so under s 74(1) or (2) might give scope for an argument that an amount paid by QBCC in respect of rectification work exceeded reasonable cost and, to that extent, was not a valid payment under the scheme.

  1. [90]
    None of those circumstances apply here. In this case, there is no reason to doubt that the claim was paid in accordance with the terms of the policy. The respondent’s detailed affidavit evidence was not relevantly challenged. The amount paid by the respondent was the cost of completing the defective work. The exhibited documents supplied particulars of the claim. The cost of completing the work was fixed by tenders, and a tender was selected.
  1. [91]
    Once the respondent proves that it made a valid payment on a claim (that is, the summary judgment brought pursuant to r 292 UCPR has been proved), then the onus shifts to the other party to show evidence of an available defence or need for trial.[22] No such defence has been shown here.

Conclusion

  1. [92]
    As matters stood on 30 October 2020 when the application for summary judgment was heard, there was no material which would properly satisfy a court that there was a real prospect of success for defending the claim. Her Honour correctly applied the relevant test for summary judgment, and was correct to find that the matters raised by the applicants did not disclose a real prospect of a defence. The applicants have not demonstrated any error on the part of the Acting Magistrate.
  1. [93]
    On the evidence, the proper conclusion was that the applicants had no real prospect of successfully defending any part of the respondent’s claim and there was nothing to suggest that there needed to be a trial of the claim or part of the claim, as provided in r 292 UCPR. The terms of r 292 were satisfied. This was an appropriate case for summary judgment.
  1. [94]
    None of the grounds relied upon in the appeal raise an issue of general application, going beyond the interests of the parties to this particular application.
  1. [95]
    None of the grounds raised by the applicants satisfy me that some important principle of law or justice is involved in the appeal, as those concepts have been explained by the authorities.

Orders

  1. [96]
    I grant leave to appeal for the sole purpose of correcting the form of the order because it was defective.
  1. [97]
    The order of the Magistrates Court of 30 October 2020 should be corrected in accordance with paragraph [24] above.
  1. [98]
    Otherwise, the application for leave to appeal is dismissed.
  1. [99]
    There is no reason why costs should not follow the event. I order that the applicants pay the respondent’s costs on the standard basis.

Footnotes

[1]See s 45(5) MCA and Queensland Civil and Administrative Tribunal Act 2009, Schedule 3.

[2]Affidavit of Grace Gunn filed 14 April 2021 Ex GG1 pp 190, 198, 261.  Annexure A to the Outline (containing the calculations) in the Magistrates Court file.

[3]By reference to Wanstall v Burke [1925] St R Qd 295, subsequently followed in Johns v Johns [1988] 1 Qd R 138.

[4]See also Baker v Arkman Pty Ltd [2014] QDC 165 at [33] and [34] per Robertson DCJ.

[5]Willmot & Anor v McLeay & Anor [2013] QCA 84 at [17]. See also Bolton Properties Pty Ltd v J K Investments (Australia) Pty Ltd [2009] 2 Qd R 202 per Daubney J.

[6]Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87 at 99.

[7]Deputy Commission of Taxation v Salcedo [2005] 2 Qd R 232 at [17].

[8]Agar v Hyde (2000) 201 CLR 552 at 575-576.

[9]Ibid.

[10]Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in liq) [2003] 1 Qd R 259 at 265.

[11]  Ibid.

[12]Deputy Commission of Taxation v Salcedo [2005] 2 Qd R 232.

[13]See Jonathan v Mangera [2016] QCA 86.

[14]The premium appears to have been paid by the homeowner’s credit card rather than by the first applicant, but nothing turns on this.

[15][2013] QCA 323.

[16]Ibid [31].

[17][2012] QSC 241 at [38].

[18][2015] 2 Qd R 1.

[19]Mr Wyatt deposed that this occurred in April 2018 but there are other documents suggesting it was in June 2018. Nothing turns on the exact date.

[20]Ibid [24].

[21][2014] QCA 161 at [33] per Gotterson JA.

[22]Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 192 at [7] per Daubney J.

Close

Editorial Notes

  • Published Case Name:

    Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission

  • Shortened Case Name:

    Full Building Solutions Pty Ltd & Burt (Wyatt) v Queensland Building and Construction Commission

  • MNC:

    [2021] QDC 77

  • Court:

    QDC

  • Judge(s):

    Fantin DCJ

  • Date:

    22 Jun 2021

Appeal Status

Please note, appeal data is presently unavailable for this judgment. This judgment may have been the subject of an appeal.

Cases Cited

Case NameFull CitationFrequency
Agar v Hyde (2000) 201 CLR 552
2 citations
American Express International Inc v Hewitt [1993] 2 Qd R 352
2 citations
Baker v Arkman Pty Ltd [2014] QDC 165
2 citations
Best Price Real Estate Pty Ltd v Equity 2 Pty Ltd [2021] QCA 99
2 citations
Bolton Properties Pty Ltd v J K Investments (Australia) Pty Ltd[2009] 2 Qd R 202; [2009] QCA 135
2 citations
Deputy Commissioner of Taxation v Salcedo[2005] 2 Qd R 232; [2005] QCA 227
3 citations
Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 192
2 citations
Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87
2 citations
Johns v Johns[1988] 1 Qd R 138; [1987] QSCFC 36
2 citations
Jonathan v Mangera [2016] QCA 86
2 citations
Mahony v Queensland Building Services Authority [2013] QCA 323
3 citations
Murdoch v Alex Mackay & Co [2017] QDC 81
2 citations
Namour v Queensland Building Services Authority[2015] 2 Qd R 1; [2014] QCA 72
2 citations
Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd [2014] QCA 161
2 citations
Queensland Building Services Authority v Orenshaw [2012] QSC 241
2 citations
Queensland University of Technology v Project Constructions (Aust) Pty Ltd (In Liq)[2003] 1 Qd R 259; [2002] QCA 224
2 citations
Ramzy v Body Corporate for GC3 CTS38396 [2012] QDC 397
2 citations
Wanstall v Burke [1925] St R Qd 295
2 citations
Willmott v McLeay [2013] QCA 84
2 citations

Cases Citing

No judgments on Queensland Judgments cite this judgment.

1

Require Technical Assistance?

Message sent!

Thanks for reaching out! Someone from our team will get back to you soon.

Message not sent!

Something went wrong. Please try again.