Exit Distraction Free Reading Mode
- Unreported Judgment
- Queensland Building and Construction Commission v Grenier Developments Pty Ltd (ACN 603 049 234)[2024] QDC 6
- Add to List
Queensland Building and Construction Commission v Grenier Developments Pty Ltd (ACN 603 049 234)[2024] QDC 6
Queensland Building and Construction Commission v Grenier Developments Pty Ltd (ACN 603 049 234)[2024] QDC 6
DISTRICT COURT OF QUEENSLAND
CITATION: | Queensland Building and Construction Commission v Grenier Developments Pty Ltd (ACN 603 049 234) & Anor [2024] QDC 6 |
PARTIES: | QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (applicant) v GRENIER DEVELOPMENTS PTY LTD (ACN 603 049 234) (first respondent) and HARSHA RAJEEWA WEERASINGHE (second respondent) |
FILE NO: | 2742/22 |
DIVISION: | Civil |
PROCEEDING: | Application |
ORIGINATING COURT: | District Court Brisbane |
DELIVERED ON: | 13 February 2024 |
DELIVERED AT: | Brisbane |
HEARING DATE: | 8 November 2023 |
JUDGE: | Farr SC, DCJ |
ORDER: |
|
CATCHWORDS: | PROFESSIONS AND TRADES – BUILDERS – STATUTORY INSURANCE SCHEME – where the first respondent was contracted to do residential building work on three separate occasions – where the second respondent was a company director of the first respondent – where the homeowners made separate complaints of defective or incomplete work – where the applicant made three separate payments under the statutory insurance scheme – where the respondent seeks a summary judgment for that debt pursuant to r 292(2) of the Uniform Civil Procedure Rules 1999 (Qld) – whether the payments made by the applicant were payments made on a claim under the statutory insurance scheme per s 71(1) of the Queensland Building and Construction Commission Act 1991 (Qld) |
LEGISLATION: | Queensland Building and Construction Commission Act 1991 (Qld) Queensland Building and Construction Commission Regulation 2018 (Qld) Uniform Civil Procedure Rules 1999 (Qld) |
CASES: | Australian Securities and Investments Commission v Cassimatis (2013) 220 FCR 256 Bellgrove v Eldridge (1954) 90 CLR 613 Deputy Commissioner of Taxation v Salcedo [2005] QCA 227 Dey v Victorian Railways Commissioners (1949) 78 CLR 62 Douglas v Tickner (1994) 49 FCR 507 Elderslie Property Investments No. 2 Pty Ltd v Dunn [2007] QSC 192 Equitrust Limited v Tucker & Ors (No. 2) [2019] QSC 248 Frontier Networks Pty Ltd v Philadelphia Developments Pty Ltd [2023] QSC 192 General Steel Industries Ltd v Commissioner for Railways (1964) 112 CLR 125 Graham Barclay Oysters Pty Ltd v Ryan [2002] HCA 54; 211 CLR 540 Howard Smith & Patrick Travel Pty Ltd v Comcare [2014] NSWCA 215 Mahony v Queensland Building Services Authority [2013] QCA 323 Namour v Queensland Building Services Authority [2014] QCA 72 Prior v South West Aboriginal Land and Sea Council Aboriginal Corporation [2020] FCA 808 Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd & Anor [2014] QCA 161 Queensland Building and Construction Commission v Turcinovic [2017] QCA 77 Queensland Building and Construction Commission v Watkins [2014] QCA 172 Robert Bax & Associates v Cavenham Pty Ltd [2011] QCA 53 Samimi & Anor v Queensland Building and Construction Commission [2015] QCA 106 Singh v Varinder Kaur (1985) 61 ALR 720 SmithKline Beecham (Australia) Pty Ltd v Chipman [2002] FCA 674 Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 ThoughtWare Australia Limited v IonMy Pty Ltd [2023] FCA 906 Tooheys Ltd v Minister for Business and Consumer Affairs (1981) 54 FLR 421 Webster v Lampard (1993) 116 ALR 545 |
COUNSEL: | NM Cooke for the applicant JM Manner for the respondents |
SOLICITORS: | Gadens Lawyers for the applicant Grasso Searles Romano Lawyers for the respondents |
Nature of application
- [1]The applicant (hereinafter referred to as the plaintiff) seeks the following orders in this application:
- Pursuant to r 292(2) of the Uniform Civil Procedure Rules 1999 (UCPR) summary judgment be granted in favour of the plaintiff against the first and second respondents (hereinafter referred to as the first and second defendants);
- Pursuant to r 293(2) of the UCPR, judgment be granted in favour of the plaintiff on the counterclaim;
- In the alternative to paragraph 1(a) and (b) above:
- Pursuant to r 171 of the UCPR, the Further Amended Defence and Counterclaim be struck out in its entirety;
- The first and second defendants to file any Second Further Amended Defence and Counterclaim within seven (7) days from the date of the orders;
- Pursuant to r 374 of the UCPR, in default of order 1(d)(ii) above, the plaintiff be entitled to proceed as if the first and second defendants have not filed a Further Amended Defence and Counterclaim; and
- The first and second defendants pay the plaintiff’s costs of, and incidental to, this application and the proceedings on the indemnity basis;
- Any such further or other order this Honourable Court deems appropriate.
- [2]The defendants submit that the application is without merit and ought be dismissed with an order for costs in favour of the defendants.
Factual background
- [3]The second defendant was a company director of the first defendant at all relevant times.
- [4]The first defendant, as a building contractor, entered into three separate agreements for residential construction works at three different locations.
- [5]The first agreement was entered into on or about 28 December 2017 for residential construction works to be completed at 20 Ellis Street, Greenslopes, Queensland 4120 (the Greenslopes project works). On or about 21 September 2018, a notice of claim was given pursuant to s 71C of the Queensland Building and Construction Commission Act 1991 (Qld) (the QBCC Act) for non-completion (the first claim).
- [6]Between on or about 1 April 2019 and on or about 28 January 2020, the plaintiff made payments totalling the amount of $197,686.54 in relation to the first claim allegedly under the Scheme pursuant to schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld) (the Regulations).
- [7]The construction allegedly had defective building work as well as incomplete building work which has been particularised in the pleadings.
- [8]The second agreement was entered into on or about 16 September 2016 for residential construction works to be completed at Lot 336 Chalk Street, Yarrabilba, Queensland 4207 (the Yarrabilba project works). On or about 7 January 2019 a notice of claim was given pursuant to s 71C of the QBCC Act for defective Yarrabilba project works (the second claim).
- [9]On or about 2 June 2020, the plaintiff made payments totalling the amount of $8,072.90 in relation to the second claim allegedly under the Scheme pursuant to schedule 6 of the Regulations.
- [10]The Yarrabilba project works allegedly had defects that are particularised in the pleadings.
- [11]The third agreement was entered into on or about 8 November 2016 for residential construction works to be completed at 26 Darien Street, Bridgeman Downs, Queensland 4035 (the Bridgeman Downs project works). On or about 14 July 2021, a notice of claim was given pursuant to s 71C of the QBCC Act for defective works (the third claim).
- [12]Between on or about 30 June 2021 and on or about 20 October 2021, the plaintiff made payments totalling $3,099.80 in relation to the third claim allegedly under the Scheme pursuant to schedule 6 of the Regulations.
- [13]The Bridgeman Downs project works allegedly had defects which are particularised in the pleadings.
- [14]The plaintiff alleges that the first defendant is liable to pay the plaintiff for sums owing in respect of the three debts totalling $208,859.24 (total debt).
- [15]The plaintiff submits that the second defendant is also liable to the plaintiff for the total debt pursuant to ss 111C(3) and 111C(6) of the QBCC Act.
The Law
Summary judgment
- [16]Rule 292 of the UCPR states:
“292Summary judgment for plaintiff
- The plaintiff may, at any time after a defendant files a notice of intention to defend, apply to the court under this part for judgment against the defendant.
- If the court is satisfied that –
- the defendant has no real prospect of successfully defending all or a part of the plaintiff’s claim; and
- there is no need for a trial of the claim or the part of the claim;
the court may give judgment for the plaintiff against the defendant for all or the part of the plaintiff’s claim and may make any other order the Court considers appropriate.”
- [17]Rule 293 of the UCPR states:
“293Summary judgment for defendant
- A defendant may, at any time after filing a notice of intention to defend, apply to the court under this part for judgment against a plaintiff.
- If the court is satisfied that –
- the plaintiff has no real prospect of succeeding on all or part of the plaintiff’s claim; and
- there is no need for a trial of the claim or the part of the claim;
the court may give judgment for the defendant against the plaintiff for all or the part of the plaintiff’s claim and may make any other order the court considers appropriate.”
- [18]In Deputy Commissioner of Taxation v Salcedo[1], Williams JA stated that in determining summary judgment under rules 292 and 293 of the UCPR:
“… the judge determining such an application is essentially called upon to determine whether the defendant to the application has established some real prospect of succeeding at a trial; if that is established then the matter must go to trial.”
- [19]In Salcedo, Atkinson J stated:
“… the court must consider whether there exists a real, as opposed to a fanciful, prospect of success. If there is no real prospect that a party will be successful in all or part of a claim, and there is no need for a trial, then ordinarily the other party is entitled to judgment.”[2]
- [20]The test to be applied is that which is set out in the rules themselves – whether it has a “real prospect of succeeding”.
- [21]So, summary judgment may only be granted if the court is satisfied that, in both the claim and counterclaim, the defendants have “no real prospects of success” in those matters and that “there is no need for a trial of the claim or part of the claim”.
- [22]The onus of persuading the court that the defendants have no real prospects of success rests on the plaintiff.[3] Although where a plaintiff leads evidence establishing a prima facie entitlement to judgment, the evidentiary onus shifts to the defendant.[4] The court then ought to focus on determining whether the defendants have placed material sufficient to persuade the court that it should not be satisfied that the defendants have no real prospects of defending the claim.[5]
- [23]The High Court has declared as a matter of general principle that “a claim for relief will be summarily dismissed as disclosing no reasonable cause of action only where it is so obviously untenable that it cannot possibly succeed.”[6] The power to order summary judgment must be exercised with “exceptional caution” and should never be exercised unless it is clear that there is no real question to be tried.[7]
- [24]Furthermore, where the nature of the proceedings involves questions of mixed fact and law, the weight of authority holds that such, typically, gives rise to a degree of complexity requiring a full hearing of the matter[8] and as such determination of the applications which seek to summarily dispense with the proceedings ought to generally be approached with particular caution by the court. In Tooheys Ltd v Minister for Business and Consumer Affairs, Ellicott J held that questions of mixed law and fact “are best determined at a final hearing when all the facts were before the court”.[9]
- [25]
“Nowhere is the need for exceptional caution more important than is a case where the ultimate outcome turns upon the resolution of some disputed issue or issues of fact. In such a case, it is essential that ‘great care’ … be exercised to ensure that under the guise of achieving expeditious finality a plaintiff is not improperly derived of his (or her) opportunity for the trial of his (or her) case by the appointed tribunal.”
- [26]Finally, I note that r 5 of the UCPR provides that the provisions must be applied in order to facilitate the just and expeditious resolution of the real issues in civil proceedings at a minimum of expense, Davis J, in Frontier Networks Pty Ltd v Philadelphia Developments Pty Ltd, held that the UCPR in respect of summary judgment provisions is not widened by the operation of r 5.[11]
Strike out
- [27]Rule 171 of the UCPR states:
“171Striking out pleadings
- This rule applies if a pleading or part of a pleading -
- discloses no reasonable cause of action or defence; or
- has a tendency to prejudice or delay the fair trial of the proceeding; or
- is unnecessary or scandalous; or
- is frivolous or vexatious; or
- is otherwise an abuse of the process of the court.
- The court, at any stage of the proceeding, may strike out all or part of the pleading and order the costs of the application to be paid by a party calculated on the indemnity basis.
- On the hearing of an application under subrule (2), the court is not limited to receiving evidence about the pleading.”
- [28]Where a plaintiff seeks to attack allegations of fact in support of a strike out application under r 171, any “apparent improbability of impugned allegation of fact does not justify the exercise of the power to strike out a pleading, because to enter upon the questions of their truth or falsehood would be trying the action prematurely.”[12]
- [29]In Robert Bax & Associates v Cavenham Pty Ltd, White JA provided that r 171 of the UCPR should apply to and will make a pleading liable for strike out where it is:
“… difficult to follow or objectively ambiguous or creates difficulty for the opposite party insofar as the pleading contains inconsistencies …”[13]
The insurance claim
- [30]The QBCC Act provides for a statutory insurance scheme to provide assistance to consumers of residential construction work for loss associated with work that is defective or incomplete.[14] Upon acceptance of the insurance premium from a licensed contractor or construction manager by the QBCC for residential construction work, it must issue a notice of cover for the work.[15] Section 68I provides that cover under the statutory insurance scheme comes into force on the earliest of the following:
- payment of the insurance premium; or
- the entry into a contract; or
- the contractor starts carrying out the work.
- [31]The plaintiff is under a duty to administer and pay out claims made under the insurance scheme.
- [32]Section 67WC defines primary insurable work. Relevantly, primary insurable work includes the erection or construction of a residence or related roofed building.
- [33]Section 67X(2) of the Act states that:
“The purpose of the statutory insurance scheme is to provide assistance to consumers of residential construction work for loss associated with work that is defective or incomplete.”
- [34]Section 67X(3) of the Act then stipulates that:
“Assistance can not be provided under the scheme to a consumer unless the consumer has suffered loss as a consequence of residential construction that is defective or incomplete.”
- [35]In respect of the terms of coverage, section 67Y states the terms of cover to which a person is entitled to assistance under the statutory insurance scheme are prescribed by regulation. Detailed terms for the statutory insurance scheme are outlined in Schedule 6 of the Regulations.
- [36]Where, as here, the QBCC indemnifies claimants under the Scheme, s 71 provides that it may recover the amount as a debt from the building contractor. Section 111C(3) and (6) of the QBCC Act also provides that if the contractor is a company, that liability also attaches to the company directors.
- [37]Section 71(1) states:
- “1.If the commission makes any payment on a claim under the statutory insurance scheme, the commission may recover the amount of the payment, as a debt, from the building contractor by whom the relevant residential construction work was, or was to be, carried out or any other person through whose fault the claim arose.”
- [38]Regulation 53 of the Regulations provides for the circumstances in which a consumer for residential construction work is not entitled to claim assistance for loss. Regulation 53(1)(i) states that:
“53.Loss caused or contributed to by particular matters
- A consumer for residential construction work is not entitled to claim assistance for loss caused or contributed to by any of the following:
…
- the act or omission of a third party, unless the loss is also caused or contributed to by:
- the licensed contractor who carried out the residential construction work or a sub- contractor, supplier or invitee of the licensed contractor; or
- an engineer, architect or building designer for the work.”
- [39]Regulation 53 defines “third party” as follows:
“‘third party’ means a person other than:
- the licensed contractor who carried out the residential construction work or a subcontractor, supplier or invitee of the licensed contractor; and
- an engineer, architect or building designer for the work”.
Plaintiff’s submissions
Greenslopes project works
- [40]The plaintiff submits that the basis for the defendants’ Further Amended Defence and Counterclaim in respect of the Greenslopes project works are matters which go to the legal quality of the determination by the plaintiff, and are not covered by any of the substantive defences expressly contained in s 71 of the QBCC Act.
- [41]It follows, so it is submitted, that the grounds for the defendants’ Further Amended Defence and Counterclaim are not justiciable at this stage of the proceedings and therefore the defendants have no real prospect of success.
- [42]Furthermore, it is submitted that the claims in the defendants’ Further Amended Defence and Counterclaim are not sustainable because:
- the allegation of non-payment under schedule 6 or any other part of the QBCC Act or the lack of a licence does not invalidate the:
- claim on the insurance policy;
- notice of acceptance of the claim; and
- the payment of the claim;
- the works performed by the plaintiff were reasonable as based on quotations for work accepted by the plaintiff. The scope of work in respect to the first claim has been upheld;[16]
- the home-owners made full payment under the contract for the sum of $115,002.90 as was requested by the plaintiff in its letter dated 21 March 2019;[17]
- the defendants have taken no steps to review or attempt to obtain a reversal of the decision taken by the QBCC to cancel the first defendant’s licence;
- cancellation of the first defendant’s licence did not excuse the defendants from undertaking and completing the contracted works; and
- the home owners affirmed the contract and paid the contract sum.[18]
Yarrabilba and Bridgeman Downs project works
- [43]The plaintiff has submitted that the claims regarding these works are very similar to the claim regarding the Greenslopes project works and accordingly the defendants’ pleadings suffer the same fatal defect in lack of justiciability.
- [44]It is submitted that the home owners suffered loss due to defective work at each property within the meaning of s 67(X) of the QBCC Act and the failure of the defendants to review or challenge, at an earlier time, the scope of work and quantum of costs is fatal to the defendants’ Further Amended Defence and Counterclaim.
The defendants’ submissions
- [45]The defendants submit that they are not liable for the amounts claimed by the plaintiff in respect of monies allegedly paid responsive to consumer claims because:
- the claims were not claims under the statutory insurance scheme as defined and contemplated by s 71(1) of the QBCC Act; and
- the alleged payments made by the plaintiff were:
- not payments on a claim made under the statutory insurance scheme pursuant to s 71(1);
- not made by the QBCC under the statutory insurance scheme as provided for and defined by part 5 of the QBCC Act.
- [46]The defendants have pleaded that the payments made by the plaintiff were:
- not made pursuant to schedule 6 of the Regulations; and
- were made contrary to s 67X(3) of the QBCC Act and r 53(1) of schedule 6 of the Regulations because:
- they were caused not as a consequence of residential construction i.e. defective or incomplete, but solely because of the actions of the QBCC; and
- the consumer had not suffered loss.
- [47]In relation to the first claim, the defendants have pleaded that any loss suffered by the consumers (which is denied) was caused solely by the QBCC and in relation to all three claims it is pleaded that the amount of monies paid by the QBCC were not reasonable and therefore not in accordance with any entitlement to a claim pursuant to r 7(1) of schedule 6 of the Regulations.
- [48]The defendants rely on the following matters in support of their position:
- the first claim arose solely by reason of the plaintiff’s negligent actions in suspending and then cancelling the building licence of the first defendant whilst the first defendant was in the process of completing the Greenslopes project works. Thus it is alleged that the plaintiff caused or contributed to the alleged loss and that r 53(1)(i) of schedule 6 of the Regulations has application;
- the consumer only suffered a loss because the plaintiff declined to engage the first defendant to complete the works at the contract amount in relation to the first claim, but subsequently expended an amount much greater than the shortfall under the contract. It is submitted therefore that the consumer did not suffer a loss as a “consequence of residential construction that is defective or incomplete” as required by s 67X(3) of the QBCC Act; and
- the amounts paid by the plaintiff in each of the claims were “exponentially” in excess of “reasonable”. This therefore makes the alleged claims extraneous to any entitlement for a claim which is limited to the consumer being entitled to claim assistance for the reasonable cost of completing the residential construction work/rectifying defective work pursuant to r 7(1) and r 15(1)(a) of schedule 6 of the Regulations.
Defendant’s submissions re counterclaim
- [49]The plaintiff suspended and then cancelled the first defendant’s builder’s licence on 3 August 2018 because the first defendant allegedly failed to satisfy the plaintiff that it had met the Minimum Financial Requirements. That cancellation occurred whilst the first defendant had completed approximately 70% of the Greenslopes project works by cost, which caused the first defendant to be unable to complete those works resulting in the contract’s termination on 28 August 2018.[19]
- [50]It is submitted that the plaintiff acted negligently in cancelling the first defendant’s building licence because the first defendant had complied with the Minimum Financial Requirements.
- [51]It is further submitted that the negligent cancellation of that licence and the plaintiff’s rejection of the first defendant’s offer to complete the Greenslopes project works and expend a vastly inflated sum for which it subsequently sought to assert liability on the part of the defendants were actions undertaken by the plaintiff in breach of its duty of care a direct consequence of which the defendants suffered loss and damage as particularised.[20]
- [52]Similar submissions are made in relation to the Yarrabilba and Bridgeman Downs project works.
- [53]The defendants also submit that due to the plaintiff’s negligence, the defendants lost the ability to undertake other building projects as from the date of the licence suspension and seek damages by way of compensation.[21]
- [54]The defendants submit that these issues are justiciable in this matter and that this is therefore not a matter where summary judgment nor the striking out of the counterclaim are appropriate.
Consideration
- [55]I agree with the defendants’ submissions that if the issues raised in their Further Amended Defence and Counterclaim are justiciable in this matter, then an order for summary judgment or the striking out of the counterclaim would not be appropriate. The matter for determination then is whether the issues as identified by the defendants in the Further Amended Defence and Counterclaim are justiciable at this stage of the proceedings.
- [56]
- [57]
- “[23]In Mahony v Queensland Building Services Authority[24]Gotterson JA, with whom Margaret McMurdo P and Douglas J agreed, said concerning recovery proceedings under the Act:
- “[31]The appellant submits that in a recovery proceeding under s 71(1), it is open to a defendant to defend the claim by challenging the legal efficacy of any step taken by the authority in the assessment of the claim. Taken to its full extent, that approach would allow the defendant to challenge the matters such as an inspection report, a decision to direct rectification of work, a decision that rectification work had not been satisfactorily attended to and a decision to accept a particular tender from those submitted for rectification work.
…
- [33]The submission invites consideration of whether such matters are justiciable in s 71(1) recovery proceedings. In my view, they are not for the following reasons.
- [34]Section 71(1) confers a right to recover as a debt from any of the designated persons ‘any payment on a claim under the insurance scheme’. It is sufficient for recovery under the section that the authority have made a payment on a claim under the insurance scheme. The statutory right to recover is not conditioned upon the legal quality of a determination by the authority to make the indemnity payment or of any anterior step taken by the authority that led to the decision to pay.
- [35]That is not to say that a decision to make an indemnity payment or any anterior step is not reviewable. At the relevant time, division 3 of part 7 of the QBSA Act conferred a review jurisdiction on the Commercial and Consumer Tribunal (‘the Tribunal’) with respect to the following decisions by the authority: to direct or not direct rectification or completion work on a building; that work undertaken at the direction of the authority was not of a satisfactory standard; about the scope of works to be undertaken under the statutory insurance scheme in order to rectify; and to disallow a claim under the scheme wholly or in part. A decision by the authority to recover an amount under s 71(1) was not reviewable by the Tribunal. However, it was a decision which was judicially reviewable in the Supreme Court of Queensland pursuant to the provisions of the Judicial Review Act 1991. So, too, for other anterior decisions of the authority. The availability of review of those kinds and at those stages provides a sound rationale for a legislative intention that the types of decisions to which I have referred, not be justiciable in s 71(1) debt recovery proceedings. Another indicator of such an intention is that s 71 itself specifies certain defences which may be raised in proceedings under the section. None of these are relevant to the kind of defence that the appellant would wish to agitate in these proceedings.
- [36]The view I take of this aspect of the construction and application of s 71(1) finds support in the following observations of Margaret Wilson AJA in Lange v Queensland Building Services Authority:
‘[72] Sections 71 and 111C provides for recovery of the amount of ‘payment on a claim under the insurance scheme’ rather than the recovery of the amount of a ‘payment under the insurance scheme’. For this reason, I do not accept counsel for the appellant’s submission that the triggering circumstance on which the respondent relies does not apply.
[73] The administrative decision sought to be reviewed is one about entitlement to indemnity under the statutory policy. The appellant is a person aggrieved by that decision because, in consequence of it, a payment was made to the owners and he was exposed to recovery proceedings pursuant to s 111C. He is entitled to seek judicial review of that decision pursuant to s 20 of the Judicial Review Act 1991.’
The triggering circumstance to which her Honour was referring was the payment by the authority of the claim.
- [37]I agree with these observations. I note that, in that case, McMurdo P and Ann Lyons J did not express a concluded view on the matter because it had not been fully argued before them. Insofar as the learned President observed that it seems unlikely that Parliament would have intended for the authority to recover from building contractors payments wrongly made to those insured by the authority on policies entered into under Part 5 of the QBSA Act, I understand her Honour to be referring to any payment that may have been made wrongly in the sense that it was not in fact upon a claim made validly under the Act. The language of s 71(1) would leave open scope for a defence that the payment sought to be recovered was not made upon a claim and a defence that the claim was not validly made under the Act. To my mind, the position was accurately summarised by Henry J in Queensland Building Services Authority v Orenshaw & Anor as follows:
‘At the other extreme, it is unlikely that s 71 could be avoided by a building contractor disputing discretionary factual conclusions occurring as part of the professional judgment exercised by the QBSA in deciding whether and how much to pay in respect of a claim. It would not be enough to avoid the statutory liability imposed by s 71 for a defendant to point merely to any error of fact connected with the claim process. It must logically have been a factual error of such a nature that the claim was not, on the facts as correctly known, a claim under the insurance scheme or that the payment sought to be recovered was not a payment on such a claim.’
(Footnotes omitted.)
…
- [25]The significance of the review avenues was again emphasised by Fraser JA in Namour v Queensland Building Services Authority[25]:
‘[14]’ The appellant relied upon Gotterson JA’s observation in Mahony that s 71(1) left open scope for a defence that the payment which was sought to be recovered ‘was not in fact made upon a claim made validly under the Act’. That reflects the text of s 71(1), but the extent of the matters which are thereby made justiciable in s 71(1) recovery proceedings was relevantly settled by the decision in Mahony. For the following reasons, matters upon which the appellant relied could not justify a conclusion in relation to any of the payments made by the respondent that the payment was not a ‘payment on a claim under the insurance scheme’ for the purposes of s 71(1).
…
- [18]… The Act conferred jurisdiction upon the Tribunal to review decisions to suspend or cancel a licence, a decision about the scope of works to be undertaken under the statutory insurance scheme to rectify or complete the relevant work, and a decision that a domestic building contract had been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme. The right of review for each decision was required to be exercised within 28 days of receiving written notice of the decision. As Gotterson JA observed in Mahony, the availability of those rights of review provides a sound rationale for a legislative intention but some decisions are not to be justiciable in debt recovery proceedings under s 71(1). That is consistent with the literal meaning of s 71(1) and, as Gotterson JA also pointed out in the same passage, the defence is allowed by subsections 71(4), (5) and (6) concern different matters.
- [19]The scheme of the Act is that a building contractor or other interested person who wishes to challenge such decisions should make the challenge before the respondent pays under the policy. A building contractor who does not make such a challenge is liable under s 71(1) whether or not those interior decisions might have been the subject of a challenge.’
(Footnotes omitted.)
- [26]In Namour Fraser JA considered the question of whether the reasonableness of a payment under the scheme was a ground of liability under s 71(1). His Honour said:[26]
‘[24]Neither the reasonableness of a payment made by the respondent nor the amount owing by a claimant under the insurance scheme to the contractor is made a criterion of liability under s 71(1). Those criteria would be relevant in a recovery action under s 71(1) only if they were relevant to the determination of the question whether the amount sought to be recovered by the respondent is the amount of the ‘payment on a claim under the insurance scheme’ …
- [25]Because there is no reason to doubt that each claim was paid in accordance with the terms of the policy, it is not necessary to decide whether or to what extent these matters might be justiciable in a recovery action under s 71(1). The detailed affidavit evidence of the respondent was not challenged; the amount paid by the respondent to each owner was the cost of completing the work reduced by the amount which remained owing to the Company under the construction contract. The exhibited documents supplied detailed particulars of each claim. The cost of completing the contract work was fixed by competitive quotes. The appellant did not identify any material which suggested that there might be a reason to doubt either the amounts shown in the documentary exhibits as being owing to the Company under the contracts or that the quoted cost of completion was reasonable (beyond an unspecified complaint that the respondent had not particularised how it took into account amounts owing to the Company and whether the payments made were reasonable).’
- [27]In Samimi & Anor v Queensland Building and Construction Commission[27] the Commission’s own material at first instance revealed a substantial inconsistency which was unexplained. It went to a circumstances of great significance and relevance to the issue of whether the money paid bv the Commission was a payment ‘on a claim under the insurance scheme’ being a payment in excess of the liability under the policy. [28] It was in this context that Boddice J (with whom Margaret McMurdo P and Morrison JA agreed) said: [29]
‘[30] The Act contains a number of mechanisms for merit reviews of decisions made by the respondent in its administration of the statutory scheme. Those review rights are wide-ranging and extensive. It is unsurprising, against that background, that s 71(1) of the Act has been interpreted as providing the respondent with a right of recovery, as a debt, of payments made by it on a claim under the insurance scheme which is not dependent upon the respondent establishing the legal correctness of a determination by it to make that payment or any anterior step taken by it that has led to the decision to pay. It is also not enough to avoid liability for a builder to point to a mere error of fact connected with the claim process.
- [31]However, it does not follow that no factual error can be the subject of a proper defence to a claim for recovery made pursuant to s 71(1) of the Act. The inclusion of the words ‘on a claim under the insurance scheme’, in s 71(1) of the Act, indicate a legislative intention to require the right of recovery to pertain to payments made ‘on’ claims under the insurance scheme. The use of those words connotes a requirement the payment made be within the policy. If that were not so, the legislature could simply have provided that the respondent could recover under s 71(1) of the Act any payment it had made pursuant to the insurance scheme.
- [32]This conclusion is consistent with the proper approach to statutory interpretation enunciated by the High Court in Lacey v Attorney-General for the State of Queensland, as ‘giving the words of a statutory provision the meaning which the legislature is taken to have intended them to have’. The interpretation contended for by the respondent would render unnecessary the inclusion of the words ‘on a claim’ in s 71(1) of the Act.
…
- [34]In agreeing with Gotterson JA’s reasons for dismissing the appeal with costs (in Mahony), the President (Margaret McMurdo P) observed:
‘In Lange, the builder contended at trial and on appeal that he was not liable under the insurance scheme created by Pt 5 Queensland Building Services Authority Act 1991 (Qld) because his clients were excluded from claiming under the scheme by cl 1.9 of the statutory insurance policy. I agreed, for the reasons given by Wilson AJA, that the primary judge rightly rejected that argument. My observations, on which the present appellant placed reliance at trial and in this appeal, should be understood in that context. Where the statutory insurer has made payments to those who were not entitled to claim under the Scheme, I presently remain unpersuaded that parliament intended, in enacting s 71(1) Queensland Building Services Authority Act, to allow the insurer to recover the amount of such payments from the builder.’ (citations omitted)
- [35]Further support for factual matters properly founding a defence to a claim for recovery under s 71(1) of the Act is derived from the observations of Fraser JA (with whose reasons the President and Douglas J agreed) in Namour v Queensland Building Services Authority:
‘Neither the reasonableness of a payment made by the respondent nor the amount owing by a claimant under the insurance scheme to the contractor is made a criterion of liability under s 71(1). Those criteria would be relevant in a recovery action under s 71(1) only if they were relevant to the determination of the question whether the amount sought to be recovered by the respondent is the amount of the ‘payment on a claim under the insurance scheme’.
- [36]Whilst Fraser JA, in Namour found the matters sought to be raised by way of defence were not justiciable under s 71(1) of the Act, that conclusion occurred in circumstances where there was ‘no reason to doubt that each claim was paid in accordance with the terms of the policy’. A different conclusion may follow where there is reason to question whether the payment was made in accordance with the terms of the policy.
- [37]Gotterson JA, in Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd & Anor also recognised that a matter of relevance to a recovery action under s 71(1) of the Act may include if the payment was not a valid payment under the scheme.
- [38]Contrary to the respondent’s submission, the consideration of whether a payment sought to be recovered under s 71(1) of the Act was a valid payment under the scheme does not merely raise an element of the respondent’s administrative processes anterior to that payment. That issue raises whether the payment was made ‘on a claim under the insurance scheme’, a condition for recovery of the payment under s 71(1) of the Act’.
(Footnotes omitted).
- [28]The review of the decisions in this Court referred to her Honour below, and the parties before us since the decision of Mahony v Queensland Building Services Authority, confirm that Mahony remains an authoritative of the law and of the liability of a building contractor to pay to the Commission the amount of any payment made ‘on a claim under the … scheme’ under s 71(1). Neither party suggested to the contrary and it should be noted that Mahony has been referred to and applied with express approval in other decisions of this Court.[30] Further, neither the judgment in Namour nor Samimi suggests, let alone establishes, any qualification or modification to the interpretation or operation of s 71(1). The availability of both internal and external review of decisions made under the Act given by Division 3 of Part 6 of the Act and of judicial review under the Judicial Review Act 1991 suggest that there is limited scope for complaint about the legal quality of the decision-making in making a payment or the decisions anterior to it. As much was expressly emphasised by Gotterson JA (with whom Margaret McMurdo P and Ann Lyons J agreed) in Queensland Building and Construction Authority v Lifetime Securities (Australia) Pty Ltd & Anor.[31]”
- [58]North J also said:
“… There is an obvious distinction to be drawn between, on the one hand, a contention that a payment was ‘so unreasonable so as to make the [payment] not a payment on a claim under the insurance scheme’ and, on the other hand, the assessment of the reasonable and necessary costs of defective building work.[32] This distinction is at the forefront of the reasoning of Fraser JA relied upon by the respondent. Further, his Honour’s reasoning maintains the distinction drawn by Margaret Wilson AJA in Lange v Queensland Building Services Authority[33] between the recovery of the amount of the ‘payment on a claim under the insurance scheme’ and the recovery of the amount of a ‘payment under the insurance scheme’. What role the question of the reasonableness of a payment might play in the determination of the recovery of a payment of the first mentioned class did not require elaboration in Namour because each claim had been paid in accordance with the terms of the policy. But that issue was central to the ultimate decision in Samimi because the evidence on behalf of the authority was contradictory, it was not clear that the claim paid was one in accordance with the terms of the policy.”
Were each of the amounts paid by the plaintiff payments on a claim under the statutory insurance scheme per s 71(1) of the QBCC Act?
- [59]The defendants submit that each of the payments in question, were not payments on a claim under the statutory insurance scheme because:
- they were not made pursuant to schedule 6 of the Act;
- were made contrary to s 67X(3) of the Act and r 53(1) of the Regulations combined because:
- they were caused not as a consequence of residential construction that is defective or incomplete, but solely because of the actions of the plaintiff; and
- the consumer had not suffered loss.
- [60]The defendants also submitted that the three claims were not claims under the statutory insurance scheme because:
- in respect of the first claim, the consumers possessed no entitlements to make claims or be paid assistance under r 53(1) of schedule 6 because any loss was caused solely by the plaintiff as a third party; and
- the monies paid were not reasonable and therefore not in accordance with any entitlement to a claim as provided under r 7(1) of schedule 6 of the Regulations.
- [61]The defendants’ argument is that r 53(1)(i) prohibits a consumer from claiming assistance for loss caused or contributed to by an act or omission of a third party. It submitted that the “third party” regarding the first claim is the plaintiff itself, and that it caused the loss by cancelling the first defendant’s building licence.
- [62]The rule defines “third party” as:
“A person other than –
- the licensed contractor who carried out the residential construction work or a subcontractor, supplier or invitee of the licensed contractor; and
- an engineer, architect or building designer for the work.”
- [63]I note that the defendants have not referred the Court to any authority in support of their pleaded position on this issue.
- [64]The plaintiff has addressed this issue by submitting that it would be absurdity for the plaintiff to fall within the category of “third party” when it was doing no more than that which it is legislatively required to do, that is, “to administer the Act”.
- [65]Furthermore, r 53(1)(i) must be read in conjunction with s 71(1). Section 71(1) provides that the commission may recover, as a debt, the amount paid on a claim under the statutory insurance scheme from the building contractor or from “any other person through whose fault the claim arose”. (My underlining).
- [66]On the defendants’ interpretation, the plaintiff would therefore be entitled to recover the amount paid on the first claim as a debt from itself because the plaintiff allegedly caused the loss suffered by cancelling the first defendant’s building licence.
- [67]Furthermore, the defendants’ interpretation ignores s 71(2)(b) which states:
“a person through whose fault the claim arose is taken to include a person who performs services for the work if the services were performed without proper care and skill”.
- [68]As Gotterson JA identified in Mahony[34], the distinction between building contractor and “a person through whose fault the claim arose” is that the former focuses on those who have contracted to carry out the work whereas the latter focuses on those who have performed the work.
- [69]It follows that the term “third party” cannot include the plaintiff – such an interpretation would lead to an absurdity.
- [70]The defendants therefore have no real prospect of succeeding on this point, and my conclusion in that regard is affirmed when consideration is given to Fraser JA’s remarks in Namour at [18]:
“Insofar as the appellant’s argument relied upon the suggested injustice of rendering the appellant liable to the respondent where the respondent had itself indirectly caused the loss by cancelling the company’s licence upon a ground which was wrong in fact, the suggested injustice is ameliorated by the building contactor’s power to seek review by an independent tribunal of the respondent’s decision to cancel the licence and of other decisions which might culminate in a claim against the contractor. The Act conferred jurisdiction upon the tribunal to review decisions to suspend or cancel a licence, a decision about the scope of works to be undertaken under the statutory insurance scheme to rectify or complete the relevant work, and a decision that a domestic building contract has been validly terminated having the consequence of allowing a claim for non-completion under the statutory insurance scheme. The right of review for each decision was required to be exercised within 28 days of receiving written notice of the decision. As Gotterson JA observed in Mahony, the availability of those rights of review provide a sound rationale for a legislative intention that some decisions are not to be justiciable in debt recovery proceedings under s 71(1). That is consistent with the literal meaning of s 71(1) and, as Gotterson JA also pointed out in the same passage, the defence is allowed by subsections 71(4), (5) and (6) concern different matters.”
Were the payments made on the claim so excessive that they were not reasonable and therefore not made on a claim under the statutory insurance scheme?
- [71]In support of this defence in relation to the first claim, the defendants rely heavily on a Non-Completion Assessment Report (the report) dated 18 January 2019 prepared by Sergon Building Consultants which stated that[35]:
- the consumers of the Greenslopes project works had paid Grenier Developments Pty Ltd 74% of the contract which left a further $114,152.90 remaining to be paid;
- the second defendant’s quote for the Greenslopes project works had been appropriately quoted and that at the time of the report the cost of completing the contract was $468,100.00;
- approximately 70% of the Greenslopes project works had been completed as at the time of the report;
- the estimated cost to complete the project was $140,430.00;
- taking into account a second builder’s setup and mobilisation costs, the cost of completion of the project was projected at $182,559.00; and
- the estimated shortfall was therefore approximately $68,406.10 to complete the Greenslopes project works.
- [72]The defendants submit that as the amount claimed for the Greenslopes project works by the plaintiff as a debt owing under a claim on the statutory insurance scheme is
$197,686.54, that is an amount which is 289% greater than the reasonably estimated cost of the shortfall.
- [73]It is submitted that this differential is so great that the amount claimed by way of debt does not arise as a result of the QBCC making any payment on a claim under the statutory insurance scheme.
- [74]The plaintiff has submitted that the process it undertook to engage a contractor to complete the project complied with the legislative requirements and involved the calling for tenders after which the least expensive tenderer was engaged.[36]
- [75]The plaintiff has also identified that the claimed amount included the sum of $10,701.24 representing the amount it paid to Sedgwick Australia Pty Ltd for building and consultancy services incurred with respect to the first claim. [37]
- [76]Furthermore, the author of the Non-Completion Assessment Report did not include the cost of rectification of defective works in his estimate of the cost of completion, whereas, the amount claimed includes the sum of $36,000 in that regard.[38]
- [77]Insofar as the second and third claims are concerned, the only evidence to support the defendants’ submission that each of the amounts paid were so excessive as to not constitute a payment on a claim (due to each of them being unreasonable) under the statutory insurance scheme comes from the second defendant offering an opinion as to the true value of the rectification work that was performed. The defendants submit that the amounts claimed were 621% and 310% greater than the amounts that the second defendant considers appropriate.[39]
- [78]This issue was addressed in Namour and Fraser JA relevantly said at [24] and [25]:
“[24]Neither the reasonableness of a payment made by the respondent nor the amount owing by a claimant under the insurance scheme to the contractor is made a criterion of liability under s 71(1). Those criteria will be relevant in a recovery action under s 71(1) only if they were relevant to the determination of the question whether the amount sought to be recovered by the respondent is the amount of the ‘payment on a claim under the insurance scheme’. The appellant argued that they were made relevant by the statutory insurance policy. The relevant provision is in cl 1.4(a), which applies where the contractor had embarked upon the contract works. In such a case, the policy limits the amount of a payment by reference to ‘[the respondent’s] assessment of the reasonable cost of completing the contract less the owner’s remaining liability under the contract (exclusive of any amount by way of liquidated damages or damages for delay) at the date of termination of the contract …’
[25]Because there is no reason to doubt that each claim was paid in accordance with the terms of the policy, it is not necessary to decide whether or to what extent these matters might be justiciable in a recovery action under s 71(1). The detailed affidavit evidence of the respondent was not challenged; the amount paid by the respondent to each owner was the cost of completing the work reduced by the amount which remained owing to the Company under the construction contract. The exhibited documents supplied detailed particulars of each claim. The cost of completing the contract work was fixed by competitive quotes. The appellant did not identify any material which suggested that there might be a reason to doubt either the amounts shown in the documentary exhibits as being owing to the Company under the contracts or that the quoted cost of completion was reasonable (beyond an unspecified complaint that the respondent had not particularised how it took into account amounts owing to the Company and whether the payments made were reasonable).”
- [79]In this matter, in respect of each claim, there is no reason to doubt that the amount in question was paid in accordance with the terms of the policy. The detailed affidavit evidence of the plaintiff supports the quantum of each claim. The choice of contractor for the Greenslopes project works was made after an appropriate tendering process and the least expensive tenderer was selected. As in Namour, the exhibited documents detailed the particulars of each claim. In relation to the second and third claims, the second defendant’s opinion as to the reasonable cost of rectification works lacks any detail and, of course, can hardly be considered to be from an independent source. In relation to the first claim, the opinion of the author of the report as to the cost of completion lacks detail and specificity and does not overcome the fact that four tenders to perform the task all quoted amounts significantly greater than the amount referred to in the report.
- [80]There is therefore no reason to doubt that each claim was paid in accordance with the terms of the policy, and that the amounts claimed represented the reasonable cost of completing the residential construction work.[40]
- [81]As Henry J said in Orenshaw at [38]:
“[38]At the other extreme, it is unlikely that s 71 could be avoided by a building contractor disputing discretionary factual conclusions occurring as part of the professional judgment exercised by the QBSA in deciding whether and how much to pay in respect of a claim. It would not be enough to avoid the statutory liability imposed by s 71 for a defendant to point merely to any error of fact connected with the claim process. It must logically have been a factual error of such a nature that the claim was not, on the facts as correctly known, a claim under the insurance scheme or that the payment sought to be recovered was not a payment on such a claim.”
- [82]Further support for this conclusion can be found in the following passage of Morrison JA in Queensland Building and Construction Commission v Turcinovic at [7]:
“Further, all of the quotes obtained by the Commission under their set Scope of Work for the Coorparoo property were well in excess of the quote by Mr Horn. When the work was approved the price was $112,022, and that was the amount on the insurance claim. There is no obvious or compelling reason to assume that the difference points to Mr Horn’s quote being correct. Indeed, where three builders all come in with a price well in excess of the quote by Mr Horn one might be tempted to think that something has gone amiss in his calculation, and look for some substantiation of his quote. That was not present here.”
- [83]And, as North J said in Turcinovic at [32]:
“The pleaded defence, that the payments were ‘so unreasonable so as to make the monies paid out not a payment on a claim under the insurance scheme’ is, in relation to each payment, no more than a rhetorical assertion designed to enliven an adjudication at the stage of debt recovery inconsistent with the operation of s 71(1). It should not be overlooked that, in respect of each payment the appellant seeks to recover, it was open to the respondent to apply for judicial review of the decision to make the payment on the ground now belatedly pleaded.”
- [84]These comments are demonstrably apposite to this matter.
- [85]Taking all these considerations into account I am of the view that the defendants have no real prospect of succeeding on this issue.
- [86]As Philippides JA said in Turcinovic at [15]:
“Section 71(1) of the Queensland Building and Construction Commission Act 1991 (Qld) should not be construed so as to permit a backdoor judicial review or a merits review of the appellant’s decision to make a payment under the statutory insurance scheme set up under the Act. Such an approach would be contrary to the statutory framework of the Act as interpreted by the authorities referred to by North J, especially Samimi v Queensland Building and Construction Commission and would not be consonant with notions of finality of decision making.”
Counterclaim
- [87]The counterclaim is a claim in negligence against the plaintiff in respect of its conduct involving the alleged negligent suspension and cancellation of the first defendant’s building licence and other alleged negligent conduct which is said to have caused loss to the first defendant.
- [88]The plaintiff has submitted that the counterclaim is doomed to fail as the QBCC, being a statutory body, does not owe a duty of care to the defendants, and even if owed, there is no evidence of behaviour on the part of the plaintiff that would amount to a breach of duty. The plaintiff also submits that the defendants are in reality, pleading a misfeasance in public office as opposed to a breach of a duty of care. If so, the plaintiff nevertheless submits that the counterclaim would still be doomed to fail as there is no evidence to support such an allegation.
- [89]The defendants however have submitted that no part of the counterclaim can be categorised as a claim in misfeasance in public office. They have affirmed that the counterclaim is a claim in negligence.
- [90]I disagree with the plaintiff’s submission that a statutory authority cannot owe a duty of care.
- [91]As Gummow and Hayne JJ said in Graham Barclay Oysters Pty Ltd v Ryan at [146],[41] the existence or otherwise of a common law duty of care allegedly owed by a statutory authority “turns upon a close examination of the terms, scope and purpose of the relevant statutory regime”. The joint reasons continued at [149]:
“An evaluation of whether a relationship between a statutory authority and a class of persons imparts a common law duty of care is necessarily a multi-faceted inquiry. Each of the salient features of the relationship must be considered. The focus of analysis is the relevant legislation and the positions occupied by the parties on the facts as found at trial. It ordinarily will be necessary to consider the degree and nature of control exercised by the authority over the risk of harm that eventuated; the degree of vulnerability of those who depend on the proper exercise by the authority of its powers; and the consistency or otherwise of the asserted duty of care with the terms, scope and purpose of the relevant statute. In particular categories of cases, some features will be of increased significance.”
- [92]The joint reasons also noted that “[t]he factor of control is of fundamental importance in discerning a common law duty of care on the part of a public authority”.[42]
- [93]Ordinarily, the determination as to whether a duty of care existed in circumstances such as are present in this matter would ordinarily be determined at trial after all evidence has been presented. However, for the purpose of this application I will proceed on the basis that the plaintiff did owe a duty of care to the first defendant to “act carefully, reasonably, skilfully, in good faith and within its power to do so when exercising or purporting to exercise powers, functions and discretions under the QBCC Act and Regulations”. [43]
Did the plaintiff act negligently and in breach of its duty of care to the first defendant in suspending and cancelling the builder’s licence?
- [94]Section 35 of the QBCC Act provides (relevantly):
35Imposition of conditions etc. on grant of licence
- A licence may be granted subject to such conditions as the authority considers appropriate.
- Without limiting subsection (1), a contractor’s licence is subject to the condition that –
- the licensee’s financial circumstances must at all times satisfy the relevant financial requirements stated in the Board’s policies.
- [95]Section 48 of the QBCC Act provides (relevantly):
48.Cancellation or suspension of licence
The authority may suspend or cancel a licence if –
…
- a licensee contravened a condition to which the licence is subject under s 35 or that is imposed under s 36 on the licensee’s licence
…
- [96]Section 49 of the QBCC Act provides (relevantly):
49.Procedure for cancellation or suspension
- The authority must, before cancelling or suspending a licence, give the licensee notice of its reasons for the proposed cancellation or suspension and allow the licensee 21 days from service of the notice to make written representations on the matter. The authority must consider any written representations made within the time allowed under subsection (1) before imposing the cancellation or suspension.
- A cancellation or suspension is imposed by written notice to the licensee.
- The notice of cancellation or suspension must inform the licensee or former licensee of the right to apply to the Tribunal for a review of the authority’s decision.
- [97]On 14 February 2018, the plaintiff commenced a Compliance Audit pursuant to s 50C of the QBCC Act.
- [98]The plaintiff received financial information for the first defendant as at 28 February 2018.
- [99]The first defendant’s balance sheet as at 28 February 2018 showed a negative net asset position of $31,578.
- [100]The minimum financial requirements policy required licensees to have Net Tangible Assets of at least $0.
- [101]The first defendant’s balance sheet included two related entity asset loans – a current loan owing from directors of $113,597, and a non-current loan owing from HRW Family Trust of $54,341.
- [102]The minimum financial requirements report (the MFR report), that was provided, only included the non-current loan in calculations.
- [103]By deducting the current related entity asset loan from calculations, the first defendant was found to have a negative Net Tangible Asset of $145,175 and a Current Ratio of 0.33;1.
- [104]On 20 March 2018, the plaintiff issued a notice of proposed suspension to the first defendant, due to the first defendant’s failure to meet the minimum financial requirements.
- [105]The notice of proposed suspension afforded the first defendant a further 21 days to make representations as to why the plaintiff should not suspend or cancel the first defendant’s licence for failure to meet the minimum financial requirements.
- [106]On 18 April 2018 and 4 May 2018, the plaintiff received correspondence from the first defendant and its accountant, making representations in response to the notice of proposed suspension.
- [107]On 18 April 2018, the first defendant provided a “revised” MFR report and balance sheet as at 28 February 2018.
- [108]The “revised” balance sheet as at 28 February 2018 included the following “revisions”:
- the removal of a current related entity asset loan owed by the directors to the first defendant of $113,597;
- the inclusion of an amount of “other debtors” of $75,000, said to be an allotment of redeemable preference shares, being share capital issued to the Cugola Family Trust;
- the inclusion of work in progress of $27,934;
- the removal of a non-current related entity asset loan owed by HRW Family Trust of $54,341;
- the amendment of trade creditors from $130,950 to $113,305, due to the assignment of three trade creditors to the Cugola Family Trust; and
- the removal of a non-current liability owed to SDC Capital Invest Loan Account of $91,928, as this loan is an equity issue of redeemable preference shares to Cugola Family Trust and not a liability.
- [109]No explanation was given for the inclusion of work in progress and removal of related entity asset loan owed by HRW Family Trust from the previously provided financial information as at 28 February 2018.
- [110]A Historical Extract search of ASIC of the company on 19 June 2018 confirmed that no document had been lodged to ASIC, as required when issuing shares, since 9 May 2016.
- [111]The Historical Extract search of ASIC of the first defendant on 19 June 2018 confirmed that the first defendant’s total number of shares issued were two.
- [112]The plaintiff was aware of a monies owed complaint lodged against the first defendant from Litewall Lightweight Building Solutions for $10,055.70 which was due for payment on 24 April 2017.
- [113]The Aged Payables listing as at 28 February 2018 showed the debt owed to Litewall Lightweight Building Solutions as current, whereas it should be correctly recorded as 90+ days.
- [114]The plaintiff reviewed the information provided, however due to the concerns outlined above, the first defendant’s licence was suspended on 21 June 2018 for failure to meet the minimum financial requirements.
- [115]On 11 July 2018, the plaintiff received an email from the accountant for the first defendant (Mr Darko) which provided particulars of the response of the first defendant to the Notice of Reasons for Proposed Cancellation.[44]
- [116]On 16 July 2018, the plaintiff provided an email response informing that notwithstanding Mr Darko’s response of 11 July 2018, the first defendant has been unable to meet the Minimum Financial Requirements. That email response noted:[45]
- three sets of balance sheets for the same reporting date of 28 February 2018 had been provided to the plaintiff, all showing different figures;
- the first balance sheet was accompanied by an MFR report which had been signed off by an accepted independent accountant and the first defendant’s director on 14 March 2018 as being true and correct and was therefore considered reliable for QBCC purposes;
- the second balance sheet was also accompanied by an MFR report which was again signed off by an accepted independent account and the company director on 18 April 2018 as being true and correct was considered therefore to be reliable for QBCC purposes;
- the third balance sheet received on 11 July 2018 was not accompanied by an MFR report;
- the issue of shares was lodged on 26 June 2018, however the previously provided MFR report which was declaring the financial information as at 28 February 2018 as being true and correct was signed off on 18 April 2018. The issue of such shares had therefore not occurred at the time of the MFR report which had been signed off by the accountant and the company director; and
- as the plaintiff had received three sets of balance sheets for the same reporting date each showing different figures, questions arose as to the reliability of the balance sheets provided such that the QBCC could not reasonably rely on the figures provided for the reporting date.
- [117]On 21 June 2018 the plaintiff issued a Notice of Reasons for Proposed Cancellation to the first defendant, due to the first defendant’s failure to meet the minimum financial requirements.
- [118]On 25 July 2018 and 26 July 2018, the plaintiff received correspondence from the first defendant, making representations to the Notice of Reasons for Proposed Cancellation, including new financial information for the first defendant as at 30 June 2018.
- [119]The plaintiff reviewed all written representations to the Notice of Reasons for Proposed Cancellation, but were nevertheless of the view that the first defendant had failed to demonstrate that it met the minimum financial requirements.
- [120]The plaintiff provided the notice of cancellation to the first defendant on 3 August 2018.
- [121]The defendants have acknowledged that the financial information provided to the plaintiff in February 2018 contained errors, but submits that those errors were corrected by the provision of correct financial details in the months that followed and that the first defendant provided further and correct conclusive information demonstrating compliance with the minimum financial requirements of the plaintiff on 30 June 2018. They submit therefore that the plaintiff cancelled the first defendant’s licence without rational basis.
- [122]That is a submission without foundation. The evidence unambiguously shows that the plaintiff exercised its powers in accordance with legislative requirements and with considerable care. The reasons for the decision to suspend and then cancel the first defendant’s licence were comprehensive, detailed and supported by evidence.
- [123]The defendants’ broad and bland assertion that by the time cancellation of the licence occurred the plaintiff was in possession of correct financial information does not in any way, on any standard, answer the reasons provided by the plaintiff for the decision to cancel.
- [124]Moreover, there is not a shred of evidence or support for the assertion that the plaintiff failed to act “carefully, reasonably, skilfully, in good faith and within its power to do so when exercising or purporting to exercise powers, functions and discretions under the QBCC Act and Regulations”.
- [125]It follows that I am satisfied that the defendants have no real prospect of success in relation to this issue and that there is no need for a trial in respect of it.
Did the plaintiff act negligently and in breach of its duty of care by failing to accept the first defendant’s offer to complete the Incomplete Works regarding the Greenslopes building project?
- [126]The plaintiff cancelled the first defendant’s licence on 3 August 2018.
- [127]On or about 27 August 2018 and 11 September 2018 the second defendant informed the consumer’s representative of the Greenslopes project works that the first defendant was willing and able to complete the works.[46] He proposed the current contract be terminated and the balance of the work be transferred, pursuant to a new contract under his medium rise builder’s licence with pricing to remain as previously agreed. I note, that in that correspondence, the second defendant acknowledged that if the consumers found such proposal to be unacceptable then the job could be transferred to another builder affiliated with the first defendant or they could choose their own builder.
- [128]On 12 September 2018 the “owners” in respect of the Greenslopes project works provided a Notice of Termination to the first defendant and advised that they will pursue a claim upon the statutory insurance scheme.
- [129]There is no doubt that the owners had a valid claim under the insurance scheme. Once made, the evidence shows that the plaintiff complied with its statutory obligations in processing the claim and in choosing another builder.
- [130]The defendants’ complain that the plaintiff acted negligently and in breach of its duty of care in not engaging the second defendant to finish the project pursuant to a new contract under his medium rise builder’s licence at no extra cost, as opposed to engaging new builders at extra cost.
- [131]This is an argument which is doomed to fail. The plaintiff cannot be said to have acted negligently or in breach of its duty of care by acting as it did. A tender process was conducted appropriately and the least expensive tender was accepted. This was an approach consistent with the statutory insurance scheme and the defendants were well aware that the course adopted was well within the rights of the plaintiff to adopt under the scheme.
- [132]Once again, I am satisfied that the defendants have no real prospects of success in relation to this issue and that there is no need for a trial in respect of it.
Orders
- The plaintiff’s application for summary judgment on the claim is allowed.
- Judgment is granted in favour of the plaintiff against the first and second defendants in the amount of $208,859.24.
- The plaintiff’s application for summary judgment on the counterclaim is allowed.
- The counterclaim is dismissed.
- I will hear the parties as to any further orders and costs.
Footnotes
[1] [2005] QCA 227 at para [17].
[2] Ibid at [47].
[3] Singh v Varinder Kaur (1985) 61 ALR 720
[4] Elderslie Property Investments No. 2 Pty Ltd v Dunn [2007] QSC 192 per Daubney J at [7].
[5] Ibid, per Daubney J at [8].
[6] Dey v Victorian Railways Commissioners (1949) 78 CLR 62 at 91; General Steel Industries Ltd v Commissioner for Railways (1964) 112 CLR 125 cited in SmithKline Beecham (Australia) Pty Ltd v Chipman [2002] FCA 674 at [30].
[7] Douglas v Tickner (1994) 49 FCR 507 at [42] per Carr J, citing General Steel Industries Ltd v Commissioner for Railways at p 129 and Dey v Victorian Railways Commissioners at p 91 and Webster v Lampard (1993) 116 ALR 545 at 548; further cited with approval in SmithKline Beecham (Australia)
[8] ThoughtWare Australia Limited v IonMy Pty Ltd [2023] FCA 906 at [50] citing Prior v South West Aboriginal Land and Sea Council Aboriginal Corporation [2020] FCA 808 at [29] and Australian Securities and Investments Commission v Cassimatis (2013) 220 FCR 256 at [49].
[9] (1981) 54 FLR 421.
[10] (1993) 116 ALR 545 at 548 per Mason CJ, Deane and Dawson JJ.
[11] [2023] QSC 192.
[12] Equitrust Limited v Tucker & Ors (No. 2) [2019] QSC 248 at [11] per Bowskill J.
[13] [2011] QCA 53 at [16].
[14] Section 67X.
[15] Sections 68B, 68C, 68F.
[16] Affidavit of Chris Chong Ping Sia of 14 September 2023 at para 18.
[17] Exhibit CS-12 to Affidavit of Chris Chong Ping Sia of 14 September 2023.
[18] Exhibit CS-47 to Affidavit of Chris Chong Ping Sia of 14 September 2023, p. 347
[19] Counterclaim paragraphs 13, 14(a) and 14(c).
[20] Counterclaim paragraphs 25-28.
[21] Page 26 of the Counterclaim.
[22] Or its predecessor the Queensland Building Services Authority Act 1991 (Qld).
[23] [2017] QCA 77.
[24] [2013] QCA 323.
[25] [2014] QCA 72 at [18] and [19]; Margaret McMurdo P and Douglas J agreeing.
[26] Namour v Queensland Building Services Authority [2014] QCA 72 at [24] and [25].
[27] [2015] QCA 106.
[28] Samimi & Anor v Queensland Building and Construction Commission [2015] QCA 106 at [26] and [27].
[29] At [30]-[38].
[30] Queensland Building and Construction Commission v Lifetime Securities (Australia) Pty Ltd & Anor [2014] QCA 161 and Queensland Building and Construction Commission v Watkins [2014] QCA 172.
[31] At [29].
[32] As to the latter, see Bellgrove v Eldridge (1954) 90 CLR 613 and Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 at [17].
[33] At [72].
[34] At [27].
[35] Ex HW-27 at p 278 to Affidavit of Harsha Rajeewa Weerasinghe filed 20 October 2023; see also Ex CS-6 at p 77 to Affidavit of Chris Chong Ping Sia affirmed 14 September 2023 – which is an almost identical report dated 21 November 2018.
[36] See Ex CS-13 at p 150 to the Affidavit of Affidavit of Chris Chong Ping Sia affirmed 14 September 2023.
[37] See Ex CS-16 to the Affidavit of Chris Chong Ping Sia affirmed 14 September 2023.
[38] See Ex CS-13 at p 150 to the Affidavit of Chris Chong Ping Sia affirmed 14 September 2023
[39] See Counterclaim para 24(d).
[40] Rule 7(1) Schedule 6 QBCC Regulations 2018.
[41] [2002] HCA 54; 211 CLR 540 ? as cited in Howard Smith & Patrick Travel Pty Ltd v Comcare [2014] NSWCA 215 at [38].
[42] At [150]; and as followed in Howard Smith & Patrick Travel Pty Ltd v Comcare [2014] NSWCA 215 at [39].
[43] Counterclaim para (15).
[44] Affidavit of Chris Chong Ping Sia affirmed 14 September 2023 at para (49).
[45] Affidavit of Chris Chong Ping Sia affirmed 14 September 2023 at para (50).
[46] Affidavit of Harsha Rajeewa Weerasinghe filed 20 October 2023 Exhibit HW-20.